Page 11 - 1.Table Of Contents.indd
P. 11

Th  rough our team’s prior experience on this site, our plan will be   Following the completion of the structure and enclosure, the team
         clearly communicated to the trades and other construction partners   will focus on the critical path elements of elevator equipment
         that will be bid and hired to execute the work.  With the prior   installation and mechanical, electrical, data rooms on the six
         understanding of the site elements, core/shell components and   fl oors where the initial tenant improvement work will begin.
         constructability lessons learned, and knowledge of coordinating   From our prior experience, the elements are critical to getting
         the tenant improvement work with the core / shell work, our team   permanent power and humidity controls for the push on the
         will be set to deliver more comprehensive GMP with a high level   interior fi nishes.  We will take the lessons learned and knowledge
         of confi dence earlier than any other team.  Our GMP philosophy   from the prior phases to keep the schedule completion dates.
         is to provide the Owner/Developer with a GMP that captures
         the complete scope of work with no gaps in construction cost.  PERMITTING
                                                                 As our team members have done in the past with the prior
         Our strategy for this project would be to develop the GMP while   phases, Barr & Barr will continue to work with the client, the
         the fi nal permit and construction documents are going through   architect and pertinent consultants to ensure all permits are
         the approval process.  Th  is will likely require and early release   coordinated with the phased construction deliverables and
         package to start the site utility, excavation, and foundation work.  construction-related permits are applied for and obtained in
                                                                 a timely manner meet the required schedule.  Our team has
         Our team’s knowledge of these components will help communicate   expedited phased core / shell documents and permit plans to
         the details to the bidding subcontractors.  We have included in the   achieve the earliest possible construction start.  We know the
         appendix of this response, local trade references from subcontractors   process to work with the City of Tampa reviewers and inspectors
         that may have been involved with the earlier phases and some   to deliver a seamless construction approach between the core/
         subcontractors we have worked with that are interested in this   shell and interior build-out scopes to insure all substantial
         project and will support Barr & Barr during the fi nal budgeting   completion and occupancy dates are achieved.
         and bidding process for the development of the GMP.
                                                                 QUALITY ASSURANCE/QUALITY CONTROL
         Our schedule would focus on getting the offi  ce building to   It is Barr & Barr’s philosophy to provide the highest quality
         production piles as quick as possible.  Th  e initial thought from   construction services to each of our clients. Our goal is to
         previous discussions would be to mobilize the offi  ce building pad   exceed all specifi ed project requirements with respect to labor,
         while the phase three area of the parking structure site would be   materials and administration of the construction process. In
         used for laydown and storage.  All traffi  c for the construction   order to meet this objective, we ensure that every requirement
         activities through the structure and enclosure will utilize this   is clearly defi ned so that it can be measured and communicated
         area to keep separation from the existing tenants.      to those responsible for its execution. It is our responsibility to
                                                                 make subjective, unquantifi able requirements tangible.
         From our knowledge of the utility requirements for the project,
         we know the storm water pond at the Southeast side of the site will   Since Offi  ce Building Th  ree is a mirror image of Offi  ce Building
         need to be enlarged to handle the storm water.  Our leadership   One, our team will be familiar with the potential constructability
         was involved in developing a storm water plan solution that is   details that could potentially aff ect schedule.  Our team will
         coordinated with the garage layout and foundation system.  With   be out in front of these issues and mitigate them before they
         this knowledge, we understand proper time needs to be accounted   become any issue.
         for in the garage schedule to insure the garage is completed with
                                                                 CONSTRUCTION SCHEDULING
         the completion/occupancy date for the offi  ce Building.  Our
                                                                 Barr & Barr will manage the Master Project Schedule and ensure
         team specifi cally worked on the solution with Civil Engineer
                                                                 commitment from all parties. We will continuously review and
         and Garage Design/Builder.
                                                                 update the schedule to monitor progress and provide solutions
                                                                 to any activities that may be tracking behind at a point in time.
         For the construction of the Offi  ce Building, our team has prior
                                                                 Th  e schedule will be an evolving tool that will be used by the
         experience in understanding the sequence of the piles and shear
                                                                 entire team to keep to the plan.  Commitment to the master
         wall/elevator shaft foundations to get out of the excavation to
                                                                 schedule is critical to achieve the established goal. Th e detailed
         get into a production mode for the vertical concrete elements.
                                                                 master schedule will include:
         Upon completion of the vertical concrete, the structural steel
                                                                 • Submittal development and approval.
         framing will be sequenced to maintain the fl oor tolerances to
                                                                 • Fabrication/long-lead times of materials and equipment
         accommodate the architectural precast spandrels to receive the
                                                                 •  Logical plan to implement the work, tied to material
         curtainwall and ribbon window elements.  Fortunately, our team
                                                                  availability
         members have history with this sequence to use as a check on the
                                                                 • Look-ahead schedules
         structural engineering to insure these tolerances are achieved.
                                                                 • Equipment commissioning
         Th  e structure and enclosure elements are critical to getting the
         building water tight for the interior fi nishes.
   6   7   8   9   10   11   12   13   14   15   16