MetLife
MetWest International and MetWest II, Tampa, FL
Relevant Team Experience
SIZE SCHEDULE OWNER ARCHITECT
200,000-SF Offi ce (2) PHASE 1 - 2007 - 2009 Metropolitan Life Insurance Thompson, Ventulett,
75,000-SF Retail PHASE 2 - 2011 - 2013 Company (MetLife) Stainback & Associates
1,700 Parking Spaces
COMPLETION DATE REFERENCE TEAM MEMBERS
CONSTRUCTION COST Phase I: January 2009 Chuck Davis, 404.838.2830 Fred Hames
Phase I: $65 Million Phase II: January 2013 Bill MIller, 404.838.2817 Matt Gilbert
Phase II: $46 Million Hank Brenner, 813.514.2433
CONTRACT TYPE Kent Walling, 813.514.2434
Construction Management
at Risk and Design-Build
PROJECT DETAILS
Th is 31+ acre redevelopment in Tampa’s prestigious Westshore District • Achieved LEED Silver Certifi cation
is being developed in multiple phases. Class A offi ce spaces totaling
• 1,462 space parking garage with a connecting
787,500-SF, a 152,000-SF executive-level hotel, 75,000-SF in restaurant
bridge
and retail buildings in a village format and a 316,000-SF residential
community with 4,200 additional parking spaces in the form of fl at
parking and garages. Th e project’s fi rst phase included the demolition of
an existing 200,000-SF offi ce building, site infrastructure; a 265,000-
SF, ten-story Class A shell offi ce building (achieved LEED® Gold
Certifi cation); 7-building restaurant/retail village and two parking garages
for over 1,700 cars. Th e retail shops, boutiques, and restaurants provide
amenity value to the redevelopment. Th e MetWest Two Development
is the project’s second phase including a new 265,000-SF, ten-story
Class A shell offi ce building. Th e structure is steel with composite concrete
decks. Th e build out of the offi ce space included meeting/training rooms
and a hot/cold cafe.