FINANCIAL
Eastern Connecticut State University
Fine Arts Instructional Center
350 High Street – Willimantic, CT CT DCS Project #BI-RW-295
I. GMP & Budget Summary
The attached budget report summary depicts the current status of the GMP, including revisions and
committed costs.
Following is the current contract summary through the period ending 7/31/2014:
- Original Contract Sum $ 61,996,682.00
- Net Change by Change Orders $ 1,043,864.78
- Contract Sum to Date $ 63,040,546.78
- Total Completed & Stored to Date $ 21,044,947.94
- Retainage $ 1,420,210.76
- Balance to Finish, Including Retainage $ 43,415,809.60