Page 11 - Transformations Brochure
P. 11
Lick-Wilmerding High School
San Francisco, CA
Size: 60.000 sf
Completion: 2018
Market: K–12 Education
As a major renovation and addition
to the campus’ main classroom and
administrative building, this project
negotiates the physical constraints of
a tight urban campus with the design
constraints of a historic building that
achieves net zero energy performance
and a LEED Platinum certification.
®
Lessons Learned
1 The surrounding context may
have changed since the original
building was constructed. Look for
opportunities to connect the new
design with its surroundings. Cumulative
2 Look at the worst part of the existing 2040 2045 2050 Emissions
(TCO2e)
building as a potential location for 2035
a major intervention. We replaced 2030
outdated toilets & locker rooms with a Pathway to Climate Positive 2025
new entry to the school. 2020 5000
Reduction from Baseline
3 Saving a historic curtain wall required
deep collaboration with the design Operational Emissions
team, contractor, and city planner to Embodied Emissions
add an interior acrylic glazing system Sequestration & Energy 0
to achieve “dual-pane” performance. Production