Page 6 - FQ10518.WayneFarms.Dothan.AL.DC25000 w15000 Gal Tank & Option
P. 6

Page No. 5
                                                                                Proposal No. Q10518
                                                                                Date:  June 12, 2017

               One (1)      Outer Wall Temperature Sensor

               One (1)      Water Recirculation Assembly Including:

                            1.      Temperature actuated switch - electronic signaling type.  (Remotely
                                    mounted in hot water tank).
                            2.      Recirculation water valve - solenoid operated.
                                    2.1  Anti-hammer diaphragm seat.

               One (1)      Safety Monitor System Including:

                            1.      Temperature actuated switches - electronic signaling.
                            2.      Level switches (water wall).
                                    Pressure switches (verifies water flow).
                            3.      Safety shut-down features are included on the Ludell water heaters that
                                    shut the heater down, if the stack temperature, water wall level, or wall
                                    temperature exceed normal operating levels.
                            4.      Automatic refire is a feature of the heater that is operational when all
                                    heater safety requirements are satisfied.  A safety shut-down will require
                                    the heater to be restarted manually in accordance with the requirements of
                                    U.L.

               One (1)      Set of Drawings Including:

                            1.      Piping schematic.
                            2.      Wiring Schematic.

               One (1)      Operating and Maintenance Manual

               Note 1 – Ludell Field Service

                       Ludell has included in its proposal the services of our field engineer for one visit, for
                       three (3) consecutive days at no added cost.  The engineer will:  inspect the equipment
                       for proper installation, adjust controls to factory standards, verify performance
                       guarantees, and instruct your personnel on the equipment features, maintenance and
                       operational use.  It is necessary to contact the Ludell Service Department two (2) weeks
                       prior to your planned equipment start-up.  Service is scheduled to begin and end during
                       the normal work week (Monday – Friday).  Normal workday is 8 hours, any overtime
                       will be billed separately.  Weekend travel and/or short term notice start-up service will
                       be charged at additional cost.  Additional trips and service will be billed on a per diem
                       basis, plus travel and living expenses at cost.

               Note II - Certified Inspection

                            All Ludell Direct Contact Water Heaters are factory inspected.
   1   2   3   4   5   6   7   8   9   10   11