Page 6 - FQ10538-R2.IconReadyMixLtd.Canada.DC5600 wOption
P. 6
Page No. 5
Proposal No. Q10538-R2
Date: September 12, 2017
One (1) Safety Monitor System Including:
1. Temperature actuated switches - electrical signaling.
2. Level switches (water wall).
3. Safety shutdown features are included on the Ludell water heaters that
shut the heater down, if the stack temperature, water wall level, or wall
temperature exceeds normal operating levels.
4. Automatic refire is a feature of the heater that is operational when all
heater safety requirements are satisfied. A safety shutdown will require
the heater to be restarted manually in accordance with the requirements of
U.L.
One (1) Set of Drawings Including:
1. Piping schematic.
2. Wiring schematic.
One (1) Operating and Maintenance Manual
Note I - Ludell Field Service
Ludell can provide the services of our field engineer at an added cost. The engineer will:
inspect the equipment for proper installation, adjust controls to factory standards, verify
performance guarantees, and instruct your personnel on the equipment features,
maintenance and operational use. It is necessary to contact the Ludell Service
Department two (2) weeks prior to your planned equipment start-up. Service is
scheduled to begin and end during the normal work week (Monday – Friday). Normal
workday is 8 hours; any overtime will be billed separately. Weekend travel and/or
short term notice start-up service will be charged at additional cost. Additional trips
and service will be billed on a per diem basis, plus travel and living expenses at cost.
Note II - Certified Inspection
All Ludell Direct Contact Water Heaters are factory inspected.