CONSTRUCTION MANAGEMENT
2.1 APPROACH It is anticipated that Building Approvals
(BA) will be obtained from a qualified
The major external and internal
constraints on the project are: Private Certifying Authority
(PCA) by the Client/Architect for all
Maintaining smooth traffic and aspects of the project, including:
pedestrians flow with minimal
disruptions to the surrounding streets; Demolition works
Undertaking works with minimal Structural works
impact on neighbours; Services and Internal Fit Out
Undertaking all works with no impact
on Students and staff. We do envisage that Staged occupation
may/will be required.
Upon commencement, our project team’s
immediate tasks will be to: 2.3 SITE SECURITY
Locate a project office, site The site will be secured using appropriate
accommodation and facilities; fences and/or hoardings
Undertake a survey of the site and The site will be secured out of hours and
complete a dilapidation report of patrolled by qualified security guards (If
surrounding properties and assets; required).
Confirm the locations of existing All visitors to the site will be required to
services and obtain all necessary report to the site office, and will be
permits and licences and approvals; appropriately inducted and registered in
and a visitor’s log book.
Arrange for the installation of
temporary services – power, water 2.4 HOARDING
and sewer to service the site works
and The Hoarding construction will consist of a
The amenities. (Where required) It is combination of timber panel wall. (MDF or
assumed provision for water and plywood as required) There will be areas
power will be provided. Separate where specific fencing, bollards, tape etc
amenities will be utilized by the may be required such as when plant is
contractors. accessing an area for a short period of
2.2 APPROVALS time.
A Development Approval is not required Note:
for the works covering the façade, Where works are required at the
excavation &basement works. boundary, temporary fence panels will be
Prior to commencing any temporary used. Gates will be used on all access
modification of traffic arrangements, points onto the site.
further approvals will be required from
ACT authorities including but not limited
to:
Application for Permit to Occupy
Road (if required for Hedge and wall
alterations)
Civil Operational Works (Where
notifiable)
24 | P a g e