Page 27 - Boss Submission Merici College
P. 27

Specific structural design details are to be          Specific contractor Design &
                 provided/reviewed by the Structural                    Construct criteria review and
                 engineer and JANDS for various aspects                 integration into project, such as:
                 of the job, such as:                               a.  JANDS pit design, inc. sump and
                                                                        access to excavated area
                 Structural Engineer                                b.  External rooftop plant stand design
                 a.  Stage extension design                         c.  External rooftop plant stand access
                 b.  Steel work connection to brickwork (re             system
                     Façade)
                 c.  Brickwork remediation                          d.  External rooftop plant stand cable,
                                                                        duct and pipework reticulation and
                 d.  Rooftop plant stand handrail                       protection
                 e.  Pit demolition/excavation                      e.  Façade connection to building
                     methodology re stage support
                                                                        brickwork
                 f.  Cassette unit installations to trussed         f.  Hydraulic management of subfloor
                     roof of science block. Considerations              drainage systems (Ref Auditorium pit)
                     for load and cutting trusses will be
                     required.
                 g.  Brickwork demolition in science                3.5 CONSTRUCTION SEQUENCE &
                                                                    PLANNING
                     corridors.
                                                                      The locations and types of plant may vary
                 JANDS
                 a.  Pit sump with regards to structure and         depending on the results of more detailed
                     function                                       planning as the design
                 b.  Electrical design for pit.                     solidifies and the availability of plant is
                                                                    firmed up. There will be 3 distinct phases
                 All structural elements that may require a         requiring different material handling logic
                 crane will have appropriate clearances             to construct the building efficiently and
                                                                    minimise impact on surrounding streets
                 obtained prior and advance notification to         and neighbours. The phases are:
                 the school will be provided. Crane areas
                 and pathways will be isolated at all times.            Phase 1. Site establishment;

                 3.4 SERVICES & FINISHES                                Demolition; Excavation and pit
                                                                        installation
                 Staging plans will be developed for all                Phase 2. Auditorium works, Science
                 mile stone events.                                     lab works and façade works
                                                                        Phase 3. System commissioning and
                 The works will be organised such that the              configuration.
                 following aspects of services installation
                 are recognised in the programme:                   *Each Phase will not happen in isolation.
                     Review and approval process for shop           Phase 2 and 3 will happen simultaneously
                     drawings                                       once the structure is sufficiently complete
                     Lead times for plant and specified             to allow the finishes trades to commence
                     materials                                      on other levels. It is assumed that:
                     DALI and CBUS procurement,
                     installation, programming and                      The school has a compliant rooftop
                     configuration                                      safety system in place.
                     AC plant and pipework                              Electricity and water can be provided.
                     AV installations (it is noted that this            Amenities will be maintained
                     may be managed by the client directly              separately by the contractor.
                     and liaison with Boss will be provided)            Onsite parking will be available in
                                                                        reasonable numbers given the scope
                                                                        of works and number of contractors
                                                                        anticipated.





                                                                                                  27 | P a g e
   22   23   24   25   26   27   28   29   30   31   32