Page 27 - Boss Submission Merici College
P. 27
Specific structural design details are to be Specific contractor Design &
provided/reviewed by the Structural Construct criteria review and
engineer and JANDS for various aspects integration into project, such as:
of the job, such as: a. JANDS pit design, inc. sump and
access to excavated area
Structural Engineer b. External rooftop plant stand design
a. Stage extension design c. External rooftop plant stand access
b. Steel work connection to brickwork (re system
Façade)
c. Brickwork remediation d. External rooftop plant stand cable,
duct and pipework reticulation and
d. Rooftop plant stand handrail protection
e. Pit demolition/excavation e. Façade connection to building
methodology re stage support
brickwork
f. Cassette unit installations to trussed f. Hydraulic management of subfloor
roof of science block. Considerations drainage systems (Ref Auditorium pit)
for load and cutting trusses will be
required.
g. Brickwork demolition in science 3.5 CONSTRUCTION SEQUENCE &
PLANNING
corridors.
The locations and types of plant may vary
JANDS
a. Pit sump with regards to structure and depending on the results of more detailed
function planning as the design
b. Electrical design for pit. solidifies and the availability of plant is
firmed up. There will be 3 distinct phases
All structural elements that may require a requiring different material handling logic
crane will have appropriate clearances to construct the building efficiently and
minimise impact on surrounding streets
obtained prior and advance notification to and neighbours. The phases are:
the school will be provided. Crane areas
and pathways will be isolated at all times. Phase 1. Site establishment;
3.4 SERVICES & FINISHES Demolition; Excavation and pit
installation
Staging plans will be developed for all Phase 2. Auditorium works, Science
mile stone events. lab works and façade works
Phase 3. System commissioning and
The works will be organised such that the configuration.
following aspects of services installation
are recognised in the programme: *Each Phase will not happen in isolation.
Review and approval process for shop Phase 2 and 3 will happen simultaneously
drawings once the structure is sufficiently complete
Lead times for plant and specified to allow the finishes trades to commence
materials on other levels. It is assumed that:
DALI and CBUS procurement,
installation, programming and The school has a compliant rooftop
configuration safety system in place.
AC plant and pipework Electricity and water can be provided.
AV installations (it is noted that this Amenities will be maintained
may be managed by the client directly separately by the contractor.
and liaison with Boss will be provided) Onsite parking will be available in
reasonable numbers given the scope
of works and number of contractors
anticipated.
27 | P a g e