CONSTRUCTION METHODOLOGY


                 3.1 SITE DESCRIPTION & LOCATION                    Science lab drainage installations on the
                                                                    ground floor will require extensive
                 The site is currently an occupied school.          excavation/remediation and detailed
                 The physical address is: 10 Wise Street,           preparatory works by licenced Asbestos
                 Braddon                                            removalists.
                 The existing building(s) affected by the
                 proposed works are:                                The drainage installation will have some
                  a.  Auditorium                                    hold points while territorial inspections are
                  b.  Science Block                                 undertaken. These will be recognised in
                  c.  External façade                               the programme as much as possible.
                 The site plan is appended at the rear of
                 this control document.                             Concrete and block installations will
                                                                    require stockpiling of materials and
                 3.2 SUBSTRUCTURE WORKS                             preparation of materials. This is proposed
                                                                    to take place in an isolated area (fence)
                 A Geotechnical report has not been                 outside the sub-floor access doors from
                 developed in concert with the structural           Wise Street to the auditorium.
                 design solutions proposed and as such
                 several hold points are anticipated in the         Specific plant, such as concrete trucks
                 basement excavation & construction                 and pumps will require a secure isolated
                 works.                                             area to deliver materials.

                 Excavation is anticipated to be clay in the        3.3 STRUCTURE
                 auditorium. No allowance has been made
                 for rock breaking if required.                     Scaffold requirements have been
                 The Science lab excavation is anticipated          considered and the most significant areas
                 to be mostly clay and base-course. No              are envisaged to be:
                 allowance for rock has been made. In all
                 instances where excavation is being                    Demolition and installation of services
                 undertaken an amount of stockpiling is                 in the Auditorium ceiling
                 expected until said waste can be                       Construction of facade steel work
                 removed.                                               Construction of external rooftop plant
                                                                        stand
                 Drainage behind the proposed pit                       Construction of Steel balcony and sail
                 blockwork has not been designed by a                   Installation of services in Science lab
                 hydraulic engineer and may require a                   ceilings
                 pump unit, access, power etc. This design              Repairs to façade area existing
                 consideration will be discussed further.               brickwork (Methodology to be
                                                                        specified)
                 Inground services alongside the building
                 where the façade works are to be                   In all instances where scaffold is required,
                 undertaken will require an in-ground               said scaffolding will have the appropriate
                 services detection prior to any invasive           certifications and barriers for isolation
                 works. The area evidences several                  from the public.
                 connected pits with shallow inverts. This
                 will impact on truck access to this area.          Scaffolding delivery, installation and
                                                                    decamp will be undertaken during
                                                                    business hours.