required for proper calibration shall be provided by the contractor.
                     Batch-type mixers may be used subject to provision of an accurate means of proportioning the
                     individual grout constituents.


                  D.  Grout Pump
                     The pump shall be of the piston type and shall have a grout pumping piston no greater than 4 in. in
                     diameter. It shall provide positive displacement of the grout and be capable of pumping at variable
                     rates of 0.2 to 2 ft³/minute at continuous pressures of as much as 1,000 lb/in²
                     The pump shall be operated within specification and capable of complete filling of the grout
                     cylinders on each stroke. It shall be equipped with a force feed or other mechanism as required to
                     ensure such complete filling. Short-stroking of the pump shall not be allowed, and any grout
                     pumped during such malfunctions shall be at the contractor’s expense.
                     A remote off-on control for the pump shall be provided at the grout injection point. An accurate
                     system to measure the quantity of grout pumped at any time interval shall be provided. The grout
                     volume measuring system shall be calibrated by the contractor each day of pumping at the
                     beginning of work and at any other time that short-stroking or a change of the grout pumping rate
                     is suspected.

                  E.  Grout Delivery Line
                     The grout delivery line shall consist of high-pressure flexible hose or a combination of hose and
                     rigid pipe- line and shall be watertight under pressure. It shall be a maximum of 2 in. diameter. All
                     components of the delivery line, including coupling clamps, shall be in good condition and capable
                     of handling the pumping pressures to be used with a minimum safety factor of 2. A pressure test of
                     the delivery line to confirm its conformance herewith shall be performed as required by the
                     engineer.

                  F.  Pressure Gauges
                     Pressure gauges shall be installed at the grout pump and at the grout header (top of hole casing).
                     All gauges shall be accurate and in good working order. They shall be protected from grout
                     intrusion by suit- able gauge protectors. Gauges shall have a minimum dial diameter of 3 in., and
                     the maximum pressure range shall be not greater than 150% of the anticipated maximum grout
                     pressure. A sufficient number of spare pressure gauges shall be maintained on the job site, and any
                     gauge of questionable accuracy shall be promptly replaced.


                3.3     FOAM GROUT EQUIPMENT
               Provide at a minimum, the following equipment:

                  A.  . Truck-Mounted Pumping Unit. Provide a truck-mounted pumping unit capable of injecting the
                      high density polyurethane material beneath the pavement. The pumping unit will be capable of
                      controlling the rate of flow of material as required to densify soils. The unit will be equipped with
                      a manufacturer’s certified flow meter to measure the amount of high-density polyurethane injected
                      at each location and will have a digital output in both pounds and gallons.

                  B.  Pressure and Temperature Control Devices. Provide pressure and  temperature  control  devices
                      capable of maintaining  proper  temperature  and proportionate mixing of the polyurethane
                      component materials.




                                                              5
               HEERUP ENGINEERING, PC                                                               January 16
               Villas at Savona                                                                         03229
   248   249   250   251   252   253   254   255   256   257   258