Page 254 - Villas at Savona Close-out Manual
P. 254

4.    DATA ACQUISITION AND REPORTING

                4.1     LOGGED INFORMATION
                     The contractor shall maintain and provide the engineer a continuous log delineating the drilling
                     and grout injection parameters for each hole. Minimum data provided on the log shall include the
                     following:

                          Date(s) and time the hole was drilled.
                          Any obstructions encountered or unusual events occurring during drilling.
                          Depth drilled and/or elevation of both the top and bottom of the hole.
                          Date(s) and time grouting of the hole was started and ended.

                          Injection pressure at the pump and at the hole collar in 3-minute intervals from the time
                          grouting starts.

                          The injected volume at each 3-minute interval.
                          Location and amount of any uplift or displacement of any structure or the ground surface
                          during grouting, if any.
                          Notation of any other observations relating to the grouting.
                     The name of the person preparing the logs and the current date shall occur on all pages of the log, and
                     the pages  shall be numbered chronologically from the start of work. The current time shall be noted at
                     each log entry.


                4.2     REAL-TIME COMPUTER MONITORING
                     Where used, the primary pressure transducer shall be located at the grout header immediately
                     above the top of the casing. As a minimum, continuous plots of both pressure and injection rate
                     shall be recorded in a time domain. Data shall be recorded in a format compatible with
                     contemporary spreadsheet software, such as Microsoft Excel, and shall be supplied to the engineer
                     in digital, and when requested printed, form. The contractor should have a suitable printer on site
                     for this purpose.

                4.3     DAILY REPORT
                     The contractor shall provide a daily report delineating the activities for each day that their people
                     are on the job site. The log shall provide at minimum the following:

                          Date
                          Weather
                          Hole numbers of holes drilled Hole numbers of holes grouted

                          Materials received and time of delivery.  Names of any visitors and time on the job site.
                          Details of any accidents, injuries, or other unusual events, including time.
                          Copies of receipts or delivery tickets for all materials delivered to the job site shall be
                          provided to the engineer.



               5.    CONSTRUCTION


                                                              6
               HEERUP ENGINEERING, PC                                                               January 16