(f) TDW may also hold stakeholders' meeting prior to the due date of
ling the response to ensure that there are no discrepancies in the
responses prepared by GOI and the mandatory respondents. The
ofcials from the concerned Departments of Central Govt. and State
Govts. may also be called for this meeting.
(g) TDW requests detailed information about the concerned schemes of
Central and State Governments for preparing the response. In case
the requested information is not received in time from the Central and
the concerned State Government, the TDW requests for the extension,
from the IAs.
(h) The TDW endeavours that Legal Counsel prepares the draft response
at least 7-days prior to the due date of ling. This draft is examined by
the TDW and sent to TPD, D/o Commerce for the vetting and
comments.
(i) The comments if any, received from the TPD are appropriately
incorporated in the GOI response.
(j) After nalization of response, approval is obtained from Nodal
Ofcer for TDW i.e. JS (TDW) or AS&DA, and the response is led by
the counsel/ TDW/EOI depending upon the provisions prescribed by
IA for ling the response.
Stage-III: Issuance of Supplementary Questionnaires
6. After submitting the response on the initial questionnaire, the IAs may
request for additional information in its supplementary questionnaire. In
case petitioner has mentioned any new schemes other than those
mentioned in petition and the initial questionnaire, the IAs issue New
Subsidy Allegations Questionnaire. Mostly the questions in the
supplementary questionnaire are specic and detailed ones and the TDW
seeks response from the concerned Ministries/ Departments, keeping in
view the strict timelines prescribed by IAs.