(f)  TDW may also hold stakeholders' meeting prior to the due date of
                    ling the response to ensure that there are no discrepancies in the
                    responses prepared by GOI and the mandatory respondents. The
                    ofcials from the concerned Departments of Central Govt. and State
                    Govts. may also be called for this meeting.

                (g)  TDW requests detailed information about the concerned schemes of
                    Central and State Governments for preparing the response.  In case
                    the requested information is not received in time from the Central and
                    the concerned State Government, the TDW requests for the extension,
                    from the IAs.

                (h)  The TDW endeavours that Legal Counsel prepares the draft response
                    at least 7-days prior to the due date of ling. This draft is examined by
                    the  TDW  and  sent  to  TPD,  D/o  Commerce  for  the  vetting  and
                    comments.

                (i)  The  comments  if  any,  received  from  the  TPD  are  appropriately
                    incorporated in the GOI response.


                (j)  After  nalization  of  response,  approval  is  obtained  from  Nodal
                    Ofcer for TDW i.e. JS (TDW) or AS&DA, and the response is led by
                    the counsel/ TDW/EOI depending upon the provisions prescribed by
                    IA for ling the response.


            Stage-III: Issuance of Supplementary Questionnaires

            6.  After submitting the response on the initial questionnaire, the IAs may
                request for additional information in its supplementary questionnaire. In
                case  petitioner  has  mentioned  any  new  schemes  other  than  those
                mentioned  in  petition  and  the  initial  questionnaire,  the  IAs  issue  New
                Subsidy  Allegations  Questionnaire.  Mostly  the  questions  in  the
                supplementary questionnaire are specic and detailed ones and the TDW
                seeks response from the concerned Ministries/ Departments, keeping in
                view the strict timelines prescribed by IAs.