Page 34 - Megaprojects Playbook
P. 34
S/Q TENET RECOMMENDED APPLICATIONS (TABLE 1)
S/Q Project Tenets Phase Mega Project All Projects
Operational Kick-off Meeting Planning X X
Generation of Safety/Quality Project Specific Plans Planning X X
Safety/Quality On-site Staffing Assessments Planning X X
Elevated Trade Partner S/Q Prequalification Analysis Planning X
Trade Partner S/Q On-site Staffing Requirements Planning X X
Trade Partner Project Specific Quality Plans Planning X X
Mobilization Infrastructure – Site Access Controls Starting X
Mobilization Infrastructure – Signage / Postings Starting X X
Mobilization Infrastructure – Conference/Support Space Starting X
S/Q Orientations / Badging Starting X X
Safety Implementation Teams (Labor) Starting X
APM-S Assignments / Duties Starting X
Utility Evaluation Surveys Starting X X
S/Q Risk Management – Risk Management Infrastructure Starting X X
S/Q Risk Management – On-Site Medical Services Starting X
Fatigue Management Program (Contractual) Starting X X
Daily Trade Supervision Coordination Meetings Executing X X
Work Implementation Plans (WIP) / Safe Work Plans (SWP) Executing X X
Risk-Based Permit Processes Executing X
Safety / Quality Committees Executing X
EMS / Fire Drills Executing X