Page 12 - Traction Distribution
P. 12

Sanction  No:  2106012,  dated:  24.06.2021.  With  this  the  sectioning  is  improved

                 between Lingampet-Jagityal and Morthad stations.











                                                                    Fig: MTPI SSP.
             Gantry modification @DKJ:


                 The BDCR bypass lines at DKJ are fed with CB-203 at DKJ/TSS. For maintenance
                 of gantry of CB-203 at DKJ/TSS power block to be availed on bypass line and
                 the  trains  coming to  the  DKJ  should  be stopped  at  PCZ.  To  avert  the  above
                 problem the gantry at DKJ is modified by erecting the isolator no. SS 303. Now
                 the  trains  can  be  entered  in  to  DKJ  even  the  power  block  is  availed  to

                 maintain the gantry of CB-203.









                                                      Fig: LOP of DKJ section

                                                                                                           rd
                Charging of New capacitor banks at KZJ and JMKT TSS in view of 3
                 line:

                 The 3rd line works between BPQ-KI is under taken by construction department
                 and  being  done  in  a  phased  manner.  Due  to  increase  in  traffic  after
                 completion of 3rd line, there will be additional requirement of reactive power
                 to cater the reactive load and to improve the power factor. As a part of this,

                 new  additional  capacitor  banks  are  commissioned  and  charged  at  KZJ  and
                 JMKT TSSs after duly competing the testing and attaining the EIG approval with
                 reference no. 2106015 & 2106018 respectively.












                        Fig: New Capacitor bank at KZJ               Fig: New capacitor bank at  JMKT/TSS