Page 4 - Traction Distribution
P. 4
CMS Crossings at 414
Yards 538
Bonding of all check rails, CMS
2 crossings and on Bridges as per Target 414
Spl. Drive No. 55 Bridges 21 17 1
Target 21
Completed
11 KV 4 4
Conversion of -11kV Power line
crossings and 33kV Power line Target 4
3
crossings with less clearances to 33 KV 33
UG crossing 1
Target 6
Out sourcing of PSI activities -
4 No. of TSS regions with TSS-20,SP-18,SSP- 0
55, AT-570
population of SPs/SPs/AT's etc.
Replacement of OHE masts
with less contact wire height
5 due to raising of track (due to 3 0
top attachment of CL reaching
max. limit)
6 Elimination of masts with Tender
implantation less than 2.50m on
6 main line in BZA-BPQ KZJ-SC 549 0 under
sections, for facilitating train process
speed of 130kmph
Action plan items for the year 2020-21:
Sl.
No. Item in brief Target Total Remarks
Provision of earthing station at Earth pits ready and
1 SSP/SP with buried rail as per RDSO 66 0 Bonding under
SMI TI/SMI/0032 progress
Isolators: Replacement with
correct connector or jumper
2 0 20 JMKT
wherever mismatch of terminal
connector Jumper is observed
Provision of Isolation facility to
3 sidings with CB/BM wherever 0 0
needed
Provision of out rigger
4 arrangement at isolators (Spl Drive: 0 2
3)
5 Provision of PTFE at all TSS locations 0 0
Erection of Model OHE at each
6 0 0
depot
Requirement of Thermo vision
7 cameras for each OHE & PSI 16 0 Further under
Depot purchase progress
Anti-falling devices for ATD to
8 cover failure of Clevis, SS rope and 0 0
etc.
Provision of Anchor Double straps
9 between ATD 9-Ton insulator and 0 7
compensating plate