Page 4 - Traction Distribution
P. 4

CMS Crossings at        414
                                                       Yards                          538
                   Bonding of all check rails, CMS
              2    crossings and on Bridges as per     Target                  414
                           Spl. Drive No. 55           Bridges                 21      17          1
                                                       Target                  21
                                                                                             Completed
                                                       11 KV                    4       4
                   Conversion of -11kV Power line
                    crossings and 33kV Power line      Target                   4
              3
                   crossings with less clearances to   33 KV                   33
                             UG crossing                                                1
                                                       Target                   6
                   Out sourcing of PSI activities -
              4    No. of TSS regions with             TSS-20,SP-18,SSP-                0
                                                       55, AT-570
                   population of SPs/SPs/AT's etc.
                   Replacement of OHE masts
                   with less contact wire height
              5    due to raising of track (due to                              3       0
                   top attachment of CL reaching
                   max. limit)
                   6 Elimination of masts with                                                  Tender
                   implantation less than 2.50m on
              6    main line in BZA-BPQ KZJ-SC                                 549      0       under
                   sections, for facilitating train                                            process
                   speed of 130kmph
           Action plan items for the year 2020-21:

             Sl.
            No.                 Item in brief                 Target     Total           Remarks
                   Provision of earthing station at                              Earth pits ready and
              1    SSP/SP with buried rail as per RDSO          66         0     Bonding under
                   SMI TI/SMI/0032                                               progress
                   Isolators: Replacement with
                   correct connector or jumper
              2                                                  0        20               JMKT
                   wherever mismatch of terminal
                   connector Jumper is observed
                   Provision of Isolation facility to
              3    sidings with CB/BM wherever                   0         0
                   needed
                   Provision of out rigger
              4    arrangement at isolators (Spl Drive:          0         2
                   3)
              5    Provision of PTFE at all TSS locations        0         0
                   Erection of Model OHE at each
              6                                                  0         0
                   depot
                   Requirement of Thermo vision
              7    cameras for each OHE & PSI                   16         0     Further under
                   Depot                                                         purchase progress
                   Anti-falling devices for ATD to
              8    cover failure of Clevis, SS rope and          0         0
                   etc.
                   Provision of Anchor Double straps
              9    between ATD 9-Ton insulator and               0         7
                   compensating plate
   1   2   3   4   5   6   7   8   9