2.  HIGHLIGHTS


               2.1.  TRACK WORKS



               2.1.1.  DEEP SCREENING OF PLAIN TRACK WITH BCM:
                       Deep screening has been done for 120.19kms against the target of
                       150.41kms  in  the  division.  SC  diviion  has  created  a  new  milestone
                       progress  of  BCM.  Division  has  acheved  a  progress  of  5.12  km
                       (4.098km  on  KRMR-PDPL  &  1.22  on  BDCR-MUGR  section)in  a  single
                       day. This is the highest ever progress any division in a single day i.e.
                       on 02/07/2021.












                                        KZJ-KI                                     BPQ-KZJ

               2.1.2.  EFFICIENCY SHIELDS:
                       SC division has received 3 major shields in civil engineering
                         Overall civil engg shiled
                         Track shield
                         Bridge shield
                       for the performance of the division in 2020-21