Page 24 - ENGINEERING
P. 24

2.1.5.  DEEP SCREENING OF PLAIN TRACK WITH HOBCM:
                       Deep  screening  has  been  done  in  SC  division  with  a    progress  of
                       54.370km  deep  screening  in  BPQ-KZJ,  PDPL-NZB,  KZJ-KI,  DKJ-MUGR,  &

                       MTMI-JNPD  sections  with  HOBCM.  2.30km  deep  screening  between
                       MCI-PPZ section with HOBCM in a single block. This is the highest ever
                       progress  achieved  in  8  hours  block  by  a  sinle  machine.  HOBCM  was
                       commissiooned for the first time in MLY-GT (UP line) section.











                                        MCI-PPZ                                  MLY-GT


               2.1.6.  TWS:
                    155 Nos of TWS has been laid till Oct’21 against proportionate  target of
                    117  Nos  in  the  division.  Full  TWS  scope  has  been  completed  in  SC-KZJ

                    section.













                                      33B MLY                                   8B in KMT

               2.1.7.  NI WORKING IN PTKP:


                     NI  work  was  started  on  11.04.2021  to  24.04.2021  at  PTKP  Yard.  4  Hours
                     block was availed everyday to complete the work.