Page 25 - ENGINEERING
P. 25

  8 No. SEJs,21 No. new TWS points and crossing were inserted for main
                       line and loop lines, 4 no. derailing switches were inserted.
                     Shifting of 1 in 8.5 switch was done by 6m using T 28 machines.

                     1 No. sand hump and  1 No. overshoot line was provided.
                     1 No. 3x tamping machine, 1 No. Duomatic CSM, 1 No. Unimat and 6
                       No. T 28 machines were  deployed
                     Cut and connection was also carried out in a block of 3 Hours at km
                       310 km at PTKP Yard.














               2.1.8.  TWS ON 2 DEGREE CURVE:
                       In the history of SC division Thick web switch (TWS) have been laid on 2
                       degree curve in contrary flexure on point no 20A DN line at WIRR yard
                       in 90 minutes.
















               2.1.9.  PQRS:
                       PQRS work has been done for  a length of 19.50KMs against the target
                       of  21.00KMs.  CTR  has  been  done  in  FNB,  NCHS,  KQD  (UP&DN),  SJVP
                       station platforms using PQRS and in PQRS, BMT, NLRD, LKPD & JET station
                       platforms using road cranes.