8 No. SEJs,21 No. new TWS points and crossing were inserted for main
line and loop lines, 4 no. derailing switches were inserted.
Shifting of 1 in 8.5 switch was done by 6m using T 28 machines.
1 No. sand hump and 1 No. overshoot line was provided.
1 No. 3x tamping machine, 1 No. Duomatic CSM, 1 No. Unimat and 6
No. T 28 machines were deployed
Cut and connection was also carried out in a block of 3 Hours at km
310 km at PTKP Yard.
2.1.8. TWS ON 2 DEGREE CURVE:
In the history of SC division Thick web switch (TWS) have been laid on 2
degree curve in contrary flexure on point no 20A DN line at WIRR yard
in 90 minutes.
2.1.9. PQRS:
PQRS work has been done for a length of 19.50KMs against the target
of 21.00KMs. CTR has been done in FNB, NCHS, KQD (UP&DN), SJVP
station platforms using PQRS and in PQRS, BMT, NLRD, LKPD & JET station
platforms using road cranes.