Page 52 - ENGINEERING
P. 52

3.1.28.  WATER TANK AT MABD:
                       New water tank has been constructed at MABD, WL, SKZR, KDM & GRP











                                     MABD                                        SKZR


               3.1.29.  PROVISION OF NEW PLATFORM AND COP AT ZAHIRABAD:
                       New  platform  No.2  was  constructed,  COP  of  3  spans  and  two  new
                       shelters  provided  on  platform  No.2.  On  P.F  No.1,  on  both  sides  of
                       station,  polished  Shahabad  flooring  surface  provided  in  place  of  the
                       damaged cement concrete flooring.












                         ZB: newly constructed pf2            ZB: newly constructed cop on PF2


               3.1.30.  HIGH LEVEL PLATFORM:
                       High  Level  Platforms  have  been  provided  in  6  nos  of  stations  ie  PNF,
                       JOA,  GTU,  KMNR,  BTPD,  LPI  against  the  annual  target  of  26  no  of
                       stations during the year in the division.












                                           KAMALNAGAR: RL PF CONVERTED TO HLPF
   47   48   49   50   51   52   53   54   55   56