3.1.16. FLOORING WORK:
shabad stone flooring work has been completed in PPY station.
3.1.17. PROVISION OF NEW PLATFORM AND COP AT ZAHIRABAD:
New platform No.2 was constructed, COP of 3 spans and two new
shelters provided on platform No.2. On P.F No.1, on both sides of station,
polished Shahabad flooring surface provided in place of the damaged
cement concrete flooring.
zahirabad: newly constructed pf2 zahirabad: newly constructed cop on pf2