               3.1.13.  IMPROVEMENT OF DRAINAGE:
                      SLIPPED BANK AT KM:79/1-3:

                       On 14.10.2020 rain fall of 115mm was recorded and heavy inundation
                       was  noticed  at  KM:79/1-3  due  to  back  flow  from  River  Kagna.
                       Inundated water was recorded within short span of time which resulted
                       in  decreased  shear  strength  leading  to  sudden  collapse  of
                       formation/bank and track. Due to this  train traffic was suspended from
                       13Hrs    of    14.10.20     to   18Hrs     of    15.10.20 and      carried     out

                       bank/track restoration work.
                      Immediately  around  100  workers  were  deputed  along  with
                      department  staff  of  TDU,  SEM  &  VKB  sections,  track  was  attended
                      manually for taking machines, Duomat packing done over manually
                      attended track, ballast unloaded .Monsoon reserve rake taken over
                      attended  track  for  strengthen  of  embankment  with  boulders  and
                      sand bags. Strengthening of bank by driving ballies and sand bags,
                      earth work by Hitachis was undertaken.