3.1.4.  RELAXATION OF LONG PENDING TSR ON BR NO 189:
                      Bridge no. 189 DN at BPQ end between RECH-RLW stations, span was
                      vibrating very badly during train movement and the slabs was getting
                      lifted  more  than  3-4  mm  for  every  train  movement.  In  view  of  this,
                      sleeper  matting  was  done  for  hard  &  level  floor  and  C.C  cribs  were
                      inserted in span above cribs with the help of 4 nos jack of each 100 ton
                      capacity. Slab was lifted 30 mm by using jack and epoxy grouting was
                      done in abutment and pier to level the top surface so that vibration of
                      slab could be stopped. After setting the epoxy, the slab lowered and
                      removed  jack  within  the  block  period.  By  taking  up  this  repair  works
                      long standing TSR of 50 kmph has been relaxed to normal speed ie.120
                      kmph and amount of Rs.55 lakh has been saved.




















               3.1.5.  BEAUTIFICATION OF LC GATES:
                           Beautification of LC gates has been done during the month in the division.













                                          LC 97                                    LC 98
   35   36   37   38   39   40   41   42   43   44   45