Page 35 - ENGINEERING
P. 35

2.1.16.  FIXING OF AUTO CHLIRINATORS IN SC-KZJ SECTION:
                    Auto chlorinators are fixed at all major colonies in SC-KZJ section.










                                     DLS/KZJ                                     ALER


               2.1.17.  INCREASING OF SPEED ON 3RD LINE:
                        The temporary speed restriction along the 3rd line between MCI-PPZ
                        was  attended  and  speed  has  been  enhanced  to  100  kmph  from
                        80kmph  over this section. This will help in improved train operations in
                        KZJ-BPQ section which is a busy and saturated section with passenger
                        and freight trains being operated at full capacity.

               2.1.18.  IMPROVEMENT OF DRAINAGE:

                      Central  drain  between  UP  &  DN  line  at  km  20/6-20/20  has  been
                      constructed  for  the  flow  of  water  in  to  the  bridge.  Last  year  at  this
                      location due to the seepage of water between the track to the DN line
                      side  embankment  was  disturbed  which  caused  unsafe  condition  for
                      the running traffic. After providing this drain water is freely flowing to the
                      br no 21. There by mitigating the problem.
   30   31   32   33   34   35   36   37   38   39   40