Page 35 - ENGINEERING
P. 35
2.1.16. FIXING OF AUTO CHLIRINATORS IN SC-KZJ SECTION:
Auto chlorinators are fixed at all major colonies in SC-KZJ section.
DLS/KZJ ALER
2.1.17. INCREASING OF SPEED ON 3RD LINE:
The temporary speed restriction along the 3rd line between MCI-PPZ
was attended and speed has been enhanced to 100 kmph from
80kmph over this section. This will help in improved train operations in
KZJ-BPQ section which is a busy and saturated section with passenger
and freight trains being operated at full capacity.
2.1.18. IMPROVEMENT OF DRAINAGE:
Central drain between UP & DN line at km 20/6-20/20 has been
constructed for the flow of water in to the bridge. Last year at this
location due to the seepage of water between the track to the DN line
side embankment was disturbed which caused unsafe condition for
the running traffic. After providing this drain water is freely flowing to the
br no 21. There by mitigating the problem.