Page 41 - ENGINEERING
P. 41

LC 100                                   LC 104

               3.1.6.  IMPROVEMENTS TO KZJ YARD:
                      As a part of improving the station, the following works were taken up at
                      KZJ station Slewing and lifting of Line No. 1 as Track machine siding.
                      Laying of 1 in 12 Scissors crossover.
                      Laying of 15 nos of TWS.
                      Renewal of isolated broken sleepers in P&Cs.
                      Scabbed & warn out rail renewal.
                      Up gradation of P&Cs from 52kg to 60kg.
                      9 nos of P&Cs Deep screening done manually.
                      Replacement of broken sleepers in apron at road no 1.
                      Crossover corrections at 112A&B, 121A&B.
                      Repairs to washable apron at washing no 1.












               3.1.7.  SAFETY IMPROVEMENT:

                       Earth  work  has  been  done  by  duly  constructing  drains  and
                       strengthening  of  embankment  at  ADEN/TDU  subdivision  under  safety
                       improvement.