3.1.8.  GOODS SIDING WORK AT ZN:
                      The following works were taken up at ZN goods siding during the block
                      time of 20 days.
                      Dismantling of old Goods line.
                      Slewing and lifting of Line No. 1 as Track machine siding.
                      Laying of 1 new point.
                      Shifting of 3 nos of OHE Masts.
                      Laying  of  New  Goods  lines  -  2  lines  of  CSR  lengths  344m  and  444m
                      respectively.
                      Laying of WBM between line No. 2 and 3 for goods loading platform.
                      Concrete  Pathway  of  150  m  length  for  Track  machine  siding  for
                      machine maintenance.
                      Provided Pre cast RCC slabs for newly developed open drain in siding
                      to ensure no water logging.











               3.1.9.  RUB PUSHING:
                       RUB work of 4 lane between SNF-HFZ stations UP & DN lines pushing has
                       been completed. Long pending  issue of state governament has been
                       fulfilled.