Page 42 - ENGINEERING
P. 42
3.1.8. GOODS SIDING WORK AT ZN:
The following works were taken up at ZN goods siding during the block
time of 20 days.
Dismantling of old Goods line.
Slewing and lifting of Line No. 1 as Track machine siding.
Laying of 1 new point.
Shifting of 3 nos of OHE Masts.
Laying of New Goods lines - 2 lines of CSR lengths 344m and 444m
respectively.
Laying of WBM between line No. 2 and 3 for goods loading platform.
Concrete Pathway of 150 m length for Track machine siding for
machine maintenance.
Provided Pre cast RCC slabs for newly developed open drain in siding
to ensure no water logging.
3.1.9. RUB PUSHING:
RUB work of 4 lane between SNF-HFZ stations UP & DN lines pushing has
been completed. Long pending issue of state governament has been
fulfilled.