Page 43 - ENGINEERING
P. 43
3.1.10. DE-LAUNCHING AND LAUNCHING OF FOB :
Old central FOB at Secunderabad was de-launched in a block of 10
hours using a crane of 150MT capacity and crane was brought inside
by placing sand bags in the gaps of sleepers, placing wooden planks
near S&T point boxes. Delaunched trussed were taken out in dip lorries
and further taken out by hydra. Launching of FOB on PF no 6/7 has
been done by using a carne of 220MT without corner weights and at a
radius of 19m by bringing the crane into road no 7 and removed the
hydrant pipe in a block of 8 hours. Further launching on PF no 8 & 10 is
planned by placing 400MT crane outside the station.
3.1.11. FOB:
In
ITEM Sanctioned Remarks
Progress
1. Completed so far: 11 Nos FOBs at
ASAF,KMNR,PBP,RAG,MDR,UDGR,ZB,MLY,
23 Nos BDCR,SC (PF 1 to 5/6)
(20 Nos under
FOB Umbrella sanction 14 Nos 2. Work in progress: 14 Nos
CMW,OEA,PTKP,MABD,LPI,MCI,DKJ,SKZR,S
and 3 Nos of C(5/6 to 10),SC (CENTRAL fob) ,
PB/LSWP items)
CT,GNN,RECH.
3. Work dropped:2 Nos KRMR,RPK
3.1.12. WORKS UNDER MGNREGS:
Jungle cleaning, cess de weeding, providing rain water harvesting
trenches along the railway boundary, clearing water way and silt
removal from drains & under water bridges in MTMI-JPTN section have
been done under MGNREGS in the division.