Page 520 - @Annual Report_PLN Batam__2019_Lowress_Neat
P. 520

5.  Melakukan Resetting Proteksi Transmisi Sistem   5.  Resetting the Protection of the Bintan System
                  Bintan sesuai kondisi Sistem  Batam.  Saat     Transmission in accordance with the conditions
                  ini settingan proteksi di sistem Bintan telah   of the Batam System. At present the protection
                  disepakati bersama.                            settings in the Bintan system have been mutually
                                                                 agreed upon.
               6.  Mengenakan Penalti kepada IPP sesuai PJBTL.   6.  Wearing Penalty to IPP according to PJBTL. The
                  Realisasi penalty telah dikenakan sesuai dengan   realization of the penalty has been imposed in
                  Berita Acara tagihan IPP periode Desember 2019.  accordance with the Minutes of the IPP bill for
                                                                 the December 2019 period.
               7.  Mempersiapkan pembangkit pengganti jika unit   7.  Preparing a replacement plant if the IPP unit fails
                  IPP gagal start atau mengalami gangguan dalam   to start or is interrupted for a long duration. PLTD
                  durasi yang lama. PLTD telah dioperasikan untuk   has been operated to reduce the power deficit
                  mengurangi defisit daya saat DEB #2 mengalami   when DEB # 2 has been disrupted since July 10,
                  gangguan sejak 10 Juli 2019.                   2019.
               Dengan demikian, maka dapat disimpulkan bahwa   Thus, it can be concluded that the management of
               pengelolaan penanganan risiko ini untuk memastikan   risk management is to ensure the availability and
               ketersediaan dan keandalan pembangkitan hanya   reliability of generation is only partially effective so
               sebagian yang efektif sehingga tetap terjadi dan   that it continues to occur and has a medium impact.
               memberikan dampak medium. Berdasarkan analisa   Based on the above analysis, we conclude that the risk
               di atas, maka kami menyimpulkan bahwa risiko   of non-optimal generation performance was initially
               Kinerja Pembangkitan Tidak Optimal ini yang awalnya   targeted at the C3 - High level, in the fourth Quarter of
               ditargetkan berada pada level C3 – Tinggi, pada   2019 the realization remained at the C3 - High level.
               Triwulan IV tahun 2019 realisasinya tetap berada
               pada level C3 – Tinggi.
            2.  Risiko Kinerja Transmisi dan GI tidak Optimal   2.  Transmission and GI Performance Risk Not Optimal
               (O.5.2)                                        (O.5.2)

                                                              This risk is basically the same as Non-Optimal
               Risiko ini pada dasarnya sama seperti Risiko   Generation Performance Risk (O.4.2 - Rising Reliability
               Kinerja Pembangkitan Tidak Optimal (O.4.2 - Risiko   Risk) which can frustrate the achievement of many
               Keandalan Pembangkitan) yang bisa menggagalkan   targets that the company has planned in the 2019
               pencapaian banyak sasaran yang sudah direncanakan   RKAP, including the PLN Batam sales growth target
               perusahaan dalam RKAP 2019, antara lain sasaran   of 3.29%; energy transfer to Bintan amounting to
               growth penjualan PLN Batam sebesar 3,29%; transfer   312,851 MWh; efficiency improvement through a 3%
               energi ke Bintan sebesar 312.851 MWh; peningkatan   reduction in NPHR from 2,513 kcal / kWh to 2,417
               efisiensi melalui penurunan NPHR 3% dari 2.513   kcal / kWh; achievement of the Customer Satisfaction
               kcal/kWh menjadi 2.417 kcal/kWh; pencapaian    Index 89.82.
               Indeks Kepuasan Pelanggan 89,82.

               Kinerja pembangkitan secara teknis dapat       The generation performance technically can affect the
               mempengaruhi kinerja transmisi dan gardu induk,   performance of the transmission and substation, and
               begitu pula sebaliknya kinerja transmisi dan   vice versa the performance of the transmission and
               gardu induk juga turut mempengaruhi kinerja    substation also affects the generation performance.
               pembangkitan. Selain kinerja pembangkitan dan   In addition to the performance of the generation
               gangguan teknis pada transmisi dan gardu induk itu   and technical interference on the transmission
               sendiri, penyebab lainnya adalah gangguan cuaca   and substation itself, other causes are weather
               yang dapat mengakibatkan gangguan sistem. Sama   disturbances that can result in system disruptions.
               seperti pembangkitan, gangguan pada transmisi dan   As with generation, disruptions to transmission and
               gardu induk dapat menyebabkan ketidakmampuan   substations can cause the company’s inability to
               perusahaan untuk menyediakan pasokan energi listrik   provide electricity for Batam. The result is a loss of
               bagi kebutuhan Batam. Akibatnya adalah hilangnya   potential selling opportunities and the effect on the
               potensi kesempatan menjual dan berpengaruh     decline in reputation and service image. Electrical
               terhadap turunnya reputasi dan citra pelayanan.   interconnection systems are at risk for protection
               Sistem kelistrikan interkoneksi berisiko terhadap   relay coordination malfunction. For that reason, the
               malfunction koordinasi relay proteksi. Untuk itu   addition of the transmission network in 2019 needs
               penambahan jaringan transmisi di tahun 2019    to increase awareness regarding coordination of
               perlu ditingkatkan kewaspadaan terkait koordinasi   system protection.
               proteksi sistem.

               Untuk mitigasinya, berikut program-program yang   For mitigation, the following programs have been
               telah direncanakan dan realisasinya sampai dengan   planned and their realization up to Quarter IV of 2019:
               Triwulan IV tahun 2019: