Page 8 - 11394_AEW_XX_XX_PP_A_0003_CO-OP PRE-CONSTRUCTION MANUAL
P. 8

1











        1A.2 Developer led project





        Stage 0








        Stage 0 relates solely to sites which are

        considered marginal by the RAM. This

        may be because of physical sizes, unique

        constraints or specific complexities that

        need to be tested prior to the instruction

        of Stage 1.




             TCG wishes to limit their exposure on marginal sites and so a limited scope
             and involvement is defined as:

             1.  The RAM identifying the marginal site and communicating this to the
             External Project Manager. Along with site location, the RAM will confirm
             TCG’s brief and requirements for the location

             2.  The External Project Manager will instruct the Architect (and Quantity
             Surveyor if Stage 0 cost appraisal is required)

             3.  The Architect will undertake a Stage 0 feasibility which at high level will
             consider the size and layout of the site against TCG’s requirements. The
             feasibility exercise considers site access / egress, physical building size and
             car park area only

             4.  The Architects Stage 0 feasibility will be used by the Quantity Surveyor (if
             required) to provide a high level cost appraisal

             5.  The External Project Manager will issue the Architects Stage 0 feasibility
             and the Quantity Surveyors high level cost appraisal to the RAM

             6.  The RAM reviews the Architects Stage 0 feasibility and Quantity
             Surveyors cost appraisal to undertake a draft Investment Appraisal [IA] to
             determine if the site should be put forward to LP&P


















































         1A.2   Developer led project             Stage 0                              0.0                                   11.10.19
   3   4   5   6   7   8   9   10   11   12   13