Page 9 - 11394_AEW_XX_XX_PP_A_0003_CO-OP PRE-CONSTRUCTION MANUAL
P. 9

RAM                             External PM                                    QS                               Architect







                     Marginal site identified








                                                           Ex.PM instructs Architect
                     RAM instructs Ex.PM of                and QS (if cost appraisal                                                     Architect undertakes
                        marginal site                      is required) to undertake                                                     Stage 0 feasibility study
                                                                Stage 0






                                                                                                                                         Architect issues Stage
                                                                                                                                         0 feasibility drawing to
                                                                                                                                            Ex.PM & QS











                                                             Stage 0 feasibility                    Stage 0 feasibility
                                                             drawing received                       drawing received









                                                                                                   QS develops Stage 0
                                                                                                     cost appraisal






                                                                                                  QS issues Stage 0 cost
                                                                                                   appraisal to Ex.PM





                                                                                                           IF REQUIRED
                                                            Ex.PM issues Stage
                     RAM receives Stage 0                   0 feasibility drawing
                     feasibility drawing and                and cost appraisal (if
                       cost appraisal                       required) to RAM to
                                                           determine site suitability








                     RAM undertakes draft
                      Investment Appraisal
                     [IA] to determine if site
                     should be put forward
                         to LP&P