Page 14 - 11394_AEW_XX_XX_PP_A_0003_CO-OP PRE-CONSTRUCTION MANUAL
P. 14

1















        1A.5 Developer led project

        Stage 3








        Stage 3 comprises the co-ordinated

        development of fit-out information post

        Scheme Approval 2, submission of

        planning applications and monitoring of

        shell construction through to Practical

        Completion.





             1.  Following Scheme Approval 2, the Ex.PM will issue an Exchange Pack of
             information to the Shell Monitor (including Shell drawings / specification and
             PCSD 06) and arrange the Exchange Meeting. Exchange Pack to be issued
             a minimum of 1 week prior to Exchange Meeting.

             2.  The Exchange Meeting (held on site for conversions only) will be
             attended by the Construction Manager, RAM, Co-op Principal Contractor,
             Internal Manager and Shell Monitor.

             3.  Following the Exchange Meeting, the External Project Manager will notify
             the design team (Architect and Principal Designer) to proceed

             4.  Simultaneously, the Construction Manager will appoint a Principal
             Contractor and provide access to I-Site for the Principal Contractor to
             examine current project information, with the exclusion of the project budget

             5.  The Architect will produce Stage 3 information including full package of
             fit-out, planning and legal drawings, co-ordinated with Structural Engineer /
             Building Services Engineer where required, and the Principal Designer will
             collate the Pre-Construction Information for issue to the team

             6.  A review of the proposed advertisements design will be undertaken by
             the Format team on receipt of the Stage 3 Architectural information and
             instruction from the External Project Manager

             7.  Once agreed, the Format team will notify the Architect and the application
             can be submitted to the LPA and monitored through to decision

             8.  Throughout the duration of the Developer’s shell construction phase, the
             Shell Monitor will conduct site visits at intervals that become increasingly
             frequent approaching Practical Completion to ensure works are proceeding
             in accordance with the agreed shell drawings and specification

             9.  At 18-6 months pre-Practical Completion of the developer’s shell, the
             Shell Monitor will conduct site visits at 3 weekly intervals, 6-3 months site
             visits at 2 weekly intervals and 3-0 months site visits at 1 weekly intervals

             10.  Following every Shell Monitor site visit, a dashboard update and
             photographic report will be provided to the Construction Manager, RAM,
             Principal Contractor, Internal Project Manager, External Project Manager,
             Quantity Surveyor, Architect and Principal Designer

             11. The first site visit [FSV] will be arranged during the shell construction
             phase for the design team to review the fit-out project programme, contract
             drawings, planning/building control/health and safety updates. The Principal
             Contractor will communicate any proposed amendments to the scheme and
             if agreed the Architect will revise the drawing information to suit

             12.  The Principal Contractor will novate the Pre-Construction Architect or
             appoint an Architect to carry out duties during the construction phase and
             notify the Construction Manager / Internal Project Manager

             13.  Shell Monitor and Developer agree Practical Completion following
             snagging and the shell is handed over



         1A.5   Developer led project             Stage 3                              0.0                                   11.10.19
   9   10   11   12   13   14   15   16   17   18   19