1       1














        1A.3 Developer led project

        Stage 1








        Stage 1 encompasses all actions

        required from identification of a

        (non-marginal) new site through to Food

        Property Board [FPB] approval and is

        defined as:




             1.  The RAM identifying the site and agreeing the site with LP&P                 12.  Upon completion of the Cost Validation 1 [CV1] Document, the Quantity
                                                                                              Surveyor will collate the Scheme Approval 1 Pack (containing CV1, Stage 1
             2.  The RAM will produce a draft Investment Appraisal [IA] and                   feasibility drawings. Asset Plan and zonal analysis) and issue to the External
             communicate the agreed site with the External Project Manager. Along with        Project Manager for their approval and comments
             the site location the RAM will confirm TCG’s brief and requirements for the
             location                                                                         13.  Once agreed the External Project Manager will submit the project
                                                                                              for Scheme Approval 1. The Internal Project Manager, External Project
             3.  The External Project Manager will instruct the Architect, the Quantity       Manager and Quantity Surveyor will be present at the Scheme Approval 1
             Surveyor and informs the Asset Team                                              Meeting

             4.  The External Project Manager will set the project plan to establish an       14.  Should the project be rejected at Scheme Approval 1, the Stage 1
             outline programme to report against within TCG and will issue the project        process will be ended and project aborted or re-worked and brought back to
             plan to the RAM, Internal Project Manager, Quantity Surveyor, Architect and      Scheme Approval 1 at a later time
             Format Team
                                                                                              15.  Should the project be approved at Scheme Approval 1 it is deemed fit to
             5.  The Architect will undertake a Stage 1 feasibility considering the site      proceed to Stage 2. During the meeting, the Quantity Surveyor will issue the
             layout including;                                                                approved Stage 1 pack and CV1 Investment Appraisal [IA] summary to the
             •   Building location and layout including BOH, FOH and external yard            RAM to obtain approval from the FPB.
                requirements, customer entrance, MOE’s and delivery access
             •   Customer parking, circulation and pedestrian routes                          16.  Following the Scheme Approval 1 Meeting the Internal Project Manager
             •   Access and egress for the delivery vehicle including preliminary swept       will complete and issue meeting minutes to the team (RAM, External Project
                path analysis                                                                 Manager, Quantity Surveyor, Architect and Format)
             •   BOH layout including freezer/chiller location, office, colleague rest area,
                bakery and WC including ventilation requirements                              17.  The RAM will notify the External Project Manager to proceed to Stage 2
                                                                                              upon FPB approval
             6.  The Architects Stage 1 feasibility will be reviewed by the External Project
             Manager and multiple options may be required until a preferred solution
             for the site is identified. This process will include liaison with TCG logistics’
             team, led by the External Project Manager

             7.  Once the preferred Stage 1 feasibility has been established, the External
             Project Manager will liaise with TCG’s Format team to establish an Asset
             Plan. The External Project Manager will provide Pre Construction Support
             Documents 00 & 01 to the Format team as a brief

             8.  The Format Team and Architects must work in conjunction to ensure the
             Stage 1 feasibility and Asset plan are co-ordinated

             9.  Once the Stage 1 feasibility and Asset Plan are co-ordinated the External
             Project Manager will notify the RAM to allow consultation with the RLA.
             Simultaneously, the Format Team will submit the Asset plan for drawing
             governance approval

             10.  Following RLA approval (desktop assessment completed by RLA), the
             RAM will instruct zonal analysis to be undertaken

             11.  Following RLA approval, drawing governance approval and completion
             of zonal analysis, the External Project Manager will notify the Quantity
             Surveyor to produce the cost plan. This notification will include confirmation
             of agreed information to date including Pre Construction Support Documents
             02, 03 & 04 completed by the External Project Manager












         1A.3   Developer led project             Stage 1                              0.0                                   11.10.19