Page 30 - 11394_AEW_XX_XX_PP_A_0003_CO-OP PRE-CONSTRUCTION MANUAL
P. 30

2









        2A.4 Developer led project


        External PM








              Task                                                          SLA           Issue        Available on   Standard form
                                                                                          Method       I-Site (/)   Stage 0 instruction (email form)
              Notified of Stage 0 marginal site from RAM
                                                                                          Email
                                                                            -
           Stage 0  Instruct Architect (and Quantity Surveyor if Stage 0 cost appraisal required)  1 day  Email      Project Plan (email form)
                                                                                                            
              Receive Stage 0 feasibility study from Architect (and cost appraisal from Quantity
                                                                                                                      Stage 0 Cost Appraisal
              Surveyor if required)                                         -             Email                      Stage 0 Feasibility drawing
              Issue Architects Stage 0 feasibility (and Quantity Surveyor cost appraisal) to RAM  1 day  Email       Stage 0 Feasibility drawing
                                                                                                                      Stage 0 Cost Appraisal

              Task                                                          SLA           Issue        Available on   Standard form
                                                                                          Method       I-Site (/)
              Notified of Stage 1 non-marginal site from RAM                -             Email                      Stage 1 instruction (email form)
              Set Project Plan and issue to RAM, Internal Project Manager, Quantity Surveyor,   1 day  Email         Project Plan (email form)
              Architect and Format team
              Instruct Architect and Quantity Surveyor to proceed with Stage 1  1 day     Email                      Project Plan (email form)
              Receives Stage 1 feasibility drawings from Architect          -             Email                      Stage 1 Feasibility drawings

              Undertake Stage 1 feasibility review and obtain agreement with TCG’s Logistics team  1 week  Email     Stage 1 Feasibility drawings
              Inform Architect if Stage 1 feasibility updates are required (multiple options may be   -  Email       -
              required until a preferred solution for the site is identified)
              Complete Pre-Construction Support Documents 00 & 01 and issue to the Format   1 week  Email            PSCD 00 – Project Info
              team as a brief to produce the Asset Plan                                                               PSCD 01 – Drawing Governance Support Document [DGSD]
           Stage 1  Receive co-ordinated Stage 1 feasibility drawings and Asset Plan from the Architect   - -  Email    Stage 1 Feasibility drawings
              and Format team and issue to the RAM
                                                                                                                      Zonal Analysis
                                                                                          Email
              Receive Zonal Analysis from RAM
                                                                                                            
              Complete PCSD’s 02, 03 and 04 and issue to the Quantity Surveyor along with   1 week  Email            PCSD 02 – Cost Validation Request Form [CVRF]
              current Stage 1 project information for Cost Validation 1 [CV1] to be developed                         PCSD 03 – Risk Register
                                                                                                                      PCSD 04 - Key Abnormals Schedule
                                                                                                                      Stage 1 Feasibility drawings
                                                                                                                      Zonal Analysis
              Receive Scheme Approval 1 package of information from Quantity Surveyor  -  Email                      Cost Validation [CV1] cost document
                                                                                                                      Stage 1 feasibility drawings
                                                                                                                      Zonal Analysis
              Review Scheme Approval 1 package of information and notify Quantity Surveyor of   1 day  Email         -
              any required updates prior to submission to Scheme Approval
              Attend Scheme Approval 1 meeting and present site with Quantity Surveyor  -  -                         -

              Receive Scheme Approval 1 meeting minutes from Internal Project Manager  -  Email                      Scheme Approval Minutes
              Notified by RAM to proceed to Stage 2 following Food Property Board [FPB] approval  -  Email           -

















































         2A.4   Developer led project             External PM                          0.0                                   11.10.19