Page 32 - 11394_AEW_XX_XX_PP_A_0003_CO-OP PRE-CONSTRUCTION MANUAL
P. 32

2









        2A.5 Developer led project


        Quantity Surveyor








              Task                                                          SLA          Issue          Available on  Standard form
                                                                                         Method         I-Site (/)
           Stage 0  Receive instruction from External Project Manager to produce Stage 0 cost appraisal  - -  Email    Project Plan (email form)
              (if required)
              Receive Stage 0 feasibility study from Architect
                                                                                                             
                                                                                                                      Stage 0 Feasibility drawing
                                                                                         Email
              Develop Stage 0 cost appraisal using Stage 0 feasibility study and issue to the   1 day  Email         Stage 0 Cost Appraisal
              External Project Manager
              Task                                                          SLA          Issue          Available on  Standard form
                                                                                         Method         I-Site (/)
              Receive Project plan from External Project Manager            -            Email                       Project Plan (email form)
              Receive PCSD’s 02, 03 and 04 and current Stage 1 project information from   -  Email                   PCSD 02 – Cost Validation Request Form [CVRF]
              External Project Manager                                                                                PCSD 03 – Risk Register
                                                                                                                      PCSD 04 - Key Abnormals Schedule
                                                                                                                      Stage 1 Feasibility drawings
                                                                                                                      Zonal Analysis
           Stage 1  Develop Cost Validation 1 [CV1] cost document           1 week       -                           Cost Validation [CV1] cost document

              Compile Scheme Approval 1 package of information and issue to the External
              Project Manager for review / updates prior to submission to Scheme Approval in   1 week  Email         Cost Validation [CV1] cost document
                                                                                                                      Stage 1 Feasibility drawings
              conjunction with the CV1 document                                                                       Zonal Analysis
              Attend Scheme Approval 1 meeting and present site with External Project Manager  1 day  -              -
              Issue Approved Stage 1 information and CV1 Investment Appraisal [IA] Summary to   1 hour  Email        CV1 IA Summary
              RAM during the Scheme Approval meeting                                                                  Stage 1 feasibility drawings
                                                                                                                      Zonal Analysis
              Receive Scheme Approval 1 meeting minutes from Internal Project Manager  -  Email                      Scheme Approval Minutes


              Task                                                          SLA          Issue          Available on  Standard form
                                                                                         Method         I-Site (/)
              Receive notification from External Project Manager of Scheme Approval 1 success   -  Email             -
              to commence Stage 2
              Attend Design Team Meeting with External Project Manager, Architect and Principal   -  Email           Design Team Meeting Agenda
              Designer
              Receive Design Team Meeting Minutes from External Project Manager  -       Email                       Design Team Meeting Minutes (Updated Agenda)
              Receive PCSD’s 00-05 and current Stage 2 project information from External Project  -  Email           PSCD 00 – Project Info
              Manager                                                                                                 PCSD 01 – Drawing Governance Support Document
                                                                                                                      PCSD 02 – Cost Validation Request Form [CVRF]
                                                                                                                      PCSD 03 – Risk Register
           Stage 2                                                                                                    PCSD 05 – Acquisition and Pre-Construction Cost
                                                                                                                      PCSD 04 Key Abnormals Schedule
                                                                                                                      Summary
                                                                                                                      Stage 2 report
                                                                                                                      PCI
              Develop Cost Validation 2 [CV2] cost document                 1 week       -                           Cost Validation [CV2] cost document
              Compile Scheme Approval 2 package of information and issue to the External   1 week  Email             Cost Validation [CV2] cost document
              Project Manager for review / updates prior to submission to Scheme Approval in                          Stage 2 report
              conjunction with the CV2 document
              Attend Scheme Approval 2 meeting and present site with External Project Manager  -  -                  -
              Issue Approved Stage 2 information and CV2 Investment Appraisal [IA] Summary to   1 hour  Email        CV2 IA Summary
              RAM during the Scheme Approval meeting                                                                  Stage 2 report
              Receive Scheme Approval 2 meeting minutes from Internal Project Manager  -  Email                      Scheme Approval Minutes


              Task                                                          SLA          Issue          Available on  Standard form
                                                                                         Method         I-Site (/)

              Receive Stage 3 drawings from Architect and PCI from Principal Designer prior to   -  Email            Stage 3 Drawings
           Stage 3  Receive Dashboard Updates and Photographic Reports from Shell Monitor   -  Email                 Dashboard Update
                                                                                                                      PCI
              submission of planning applications
              throughout the during of the Developer’s shell construction phase
                                                                                                                      Photographic Report
              Attend First Site Visit [FSV] during Developer’s shell construction phase with the   1 day  Email      Pre-start Meeting Agenda
              design team to review project documents / information
              Receive FSV meeting minutes from External Project Manager     -            Email                       Pre-start Meeting Minutes (updated Agenda)
















         2A.5   Developer led project             Quantity Surveyor                    0.0                                   11.10.19