               comfort, energy use, durability, and maintenance.       ■ Record and distribute minutes from consultant
               During this phase, the Bernardon Team will complete     coordination meetings and design meetings with
               the following tasks and provide the listed deliverables:  the Owner.
                                                                       ■ Prepare a detailed code analysis for review with
                  ■ Based on AtlantiCare’s approval of the conceptual   the appropriate agencies before proceeding to the
                  design, the Bernardon Team will prepare Schematic    Design Development Phase. Meet with Authorities
                  Design Documents for AtlantiCare’s approval.         Having Jurisdiction (AHJ) over the project (local,
                  The Schematic Design Documents will consist of       county, and state municipalities;) to review plans
                  drawings and other documents including a site        and code related issues.
                  plan,  preliminary  building plans, sections and     ■ Attend public hearings and meetings for local
                  elevations, and  may include  some  combination      and municipal approvals, and provide graphics
                  of  perspective  sketches  and/or digital modeling.     and testimony as required.  Eight (8) hours are
                  Preliminary selections of major building systems     included for such meetings.
                  and  construction  materials  will  be  noted  on the     ■ The Bernardon Team will coordinate with the
                  drawings or described in writing.                    Construction Manager who will perform an
                  ■ Continue to evaluate and refine the program        estimate of  the  Cost  of  the Work, and  we  will
                  requirements.                                        participate in an estimate review session with
                  ■ Advise the Owner and Project Manager in writing    the Owner, Project Manager, and Construction
                  if at any time it appears that the Project Schedule   Manager. We will also participate in any value
                  or Construction Budget may be exceeded and make      analysis sessions structured to improve the design
                  recommendations for corrective action.               or reduce the overall construction cost.
                  ■ Meet with the Owner and Project Manager at         ■ The Bernardon Team will revise the Schematic
                  mutually agreeable intervals to review drawings      Design Documents to comply with the target
                  and other documents which represent the current      construction budget if the construction cost
                  status of the Schematic Design of the Project.       estimate exceeds the approved budget and as
                  ■ The Bernardon Team will consider environmentally   directed to do so by the Project Manager.
                  responsible design alternatives, such as material     ■ Deliverables: During this phase, the Bernardon
                  choices and building orientation together with       Team will prepare and submit the following
                  other considerations based on the program and        deliverables to AtlantiCare.  All such deliverables
                  aesthetics, in developing a design for the Project   will be subject to review and approval by
                  that is consistent with the program, schedule, and   AtlantiCare.    It  is  understood  that  revisions
                  budget.                                              may be required to these documents to address
                  ■ The Bernardon Team will consider the value of      concerns  raised  by AtlantiCare  and/or  other
                  alternative  materials,  building  systems  ,and     Project stakeholders. Work product delivered will
                  equipment, together with other considerations        be owned by AtlantiCare.
                  based on the program and aesthetics, in developing      o Updated site plan and building plans, sections,
                  a design for the Project that is consistent with the    and elevations illustrating the Project’s scale
                  program, schedule and budget.                           and the relationship of the Project components
                                                                          to one another and the relationship of the
                                                                          Project to surrounding properties.


               BERNARDON | Response to Request for Proposal Architectural and Engineering  Services
               AtlantiCare Health Services | Manahawkin Ambulatory Surgery Center | June 7, 2021      Page 21
   21   22   23   24   25   26   27   28   29   30   31