Page 4 - Graypvine August 2021
P. 4

House the steam piping, process utility piping and    will begin. The waste water treatment scope of
            process piping continues, and the compressed          work shall also begin near the end of this month
            air and control wiring installation has begun.        and be complete the following month. All activities
            Warehouse #1 has been turned over to Diageo and       were wrapping up as we neared our substantial
            they are storing bourbon barrels from an off-site     completion date of July 23rd.
            Distillery. Warehouse #2 metal siding and roofing       Since the last update for the Marzetti Dressing
            installation is ongoing and Warehouse #3 and #4       Plant Expansion located in Horse Cave, KY, the
            slab pours are almost complete.                       Phase 1 ingredient receiving warehouse was
              Amazon Project Caprock in Visalia, California       enclosed and is being fitted up as temporary
            reached our tenth and final turnover on June 21st.    office and employee services space. The transition
            Essentially the entire building has been turned       from existing office to this temporary space was
            over to Amazon. Our TCO was completed on July         scheduled for July 9th. This allowed the demolition
            12th. All asphalt and concrete paving has been        of the existing office so construction of the
      4     completed on site. We are still working on offsite    production and new office areas can continue. New
                                                                  employee parking lots have been paved while site
            improvements and road widening but that should
            be completed by July 25th. Permanent power            utilities continue to be installed. Foundations in the
            was live in mid-June, and once the power was live     main expansion area are 60% complete as work
            we began start-up of the RTU’s and started the        in the kitchen pits has begun, and structural steel
            commissioning process. Amazon’s first receive is      is roughly 30% complete. Underground piping and
            August 16th.                                          electrical work continue. Planning shutdowns for
              Another project for Amazon, Project Panda           utility and ingredient tie-ins is a particular focus right
            is in full swing with the 3.8 million s.f. fulfillment   now. Process and controls engineering and design
            center at the former Michigan State Fairgrounds in    continues, while long-lead equipment purchasing
            Detroit. Gray and the developer continue to work      is well underway. The project is scheduled to
            closely with the City of Detroit on various aspects   complete in July 2022.
            of this revitalization project, which also includes     Owens Corning Project Razor is pushed through
            construction of new public roadways, transit center   a very wet Arkansas spring. Along with site
            and utility improvements.                             development, storm water piping began installation
              With the project consisting of 20,000 tons of       in mid-June and the excavation and shoring of the
            structural steel and joists, steel is now topped      33’ deep basement pit is around 50% complete.
            out on the 5-story main structure. Slab pours are     The foundations for the 420,000 s.f. warehouse
            approaching 50% complete. Precast, IMP, roofing       portion of the facility are nearing completion and
            and metal stud walls are in progress. Building utility   slab pours began at the end of June. The first
            systems are being installed as we work towards        shipments of the Pre-Engineered Building also
            a helicopter lift at the end of July and permanent    arrived at the end of June and erection of the
            power in mid-August. We’ll turn over the first area   warehouse began in early July.
            to the tenant and their MHE vendors at the end
            of September.
              On the MKDA jobsite, we are currently preparing
            for finish trades to begin their work in the office
            area and mechanical piping throughout the
            production areas continue. By the end of the
            month paving will be complete and landscaping