House the steam piping, process utility piping and will begin. The waste water treatment scope of
process piping continues, and the compressed work shall also begin near the end of this month
air and control wiring installation has begun. and be complete the following month. All activities
Warehouse #1 has been turned over to Diageo and were wrapping up as we neared our substantial
they are storing bourbon barrels from an off-site completion date of July 23rd.
Distillery. Warehouse #2 metal siding and roofing Since the last update for the Marzetti Dressing
installation is ongoing and Warehouse #3 and #4 Plant Expansion located in Horse Cave, KY, the
slab pours are almost complete. Phase 1 ingredient receiving warehouse was
Amazon Project Caprock in Visalia, California enclosed and is being fitted up as temporary
reached our tenth and final turnover on June 21st. office and employee services space. The transition
Essentially the entire building has been turned from existing office to this temporary space was
over to Amazon. Our TCO was completed on July scheduled for July 9th. This allowed the demolition
12th. All asphalt and concrete paving has been of the existing office so construction of the
4 completed on site. We are still working on offsite production and new office areas can continue. New
employee parking lots have been paved while site
improvements and road widening but that should
be completed by July 25th. Permanent power utilities continue to be installed. Foundations in the
was live in mid-June, and once the power was live main expansion area are 60% complete as work
we began start-up of the RTU’s and started the in the kitchen pits has begun, and structural steel
commissioning process. Amazon’s first receive is is roughly 30% complete. Underground piping and
August 16th. electrical work continue. Planning shutdowns for
Another project for Amazon, Project Panda utility and ingredient tie-ins is a particular focus right
is in full swing with the 3.8 million s.f. fulfillment now. Process and controls engineering and design
center at the former Michigan State Fairgrounds in continues, while long-lead equipment purchasing
Detroit. Gray and the developer continue to work is well underway. The project is scheduled to
closely with the City of Detroit on various aspects complete in July 2022.
of this revitalization project, which also includes Owens Corning Project Razor is pushed through
construction of new public roadways, transit center a very wet Arkansas spring. Along with site
and utility improvements. development, storm water piping began installation
With the project consisting of 20,000 tons of in mid-June and the excavation and shoring of the
structural steel and joists, steel is now topped 33’ deep basement pit is around 50% complete.
out on the 5-story main structure. Slab pours are The foundations for the 420,000 s.f. warehouse
approaching 50% complete. Precast, IMP, roofing portion of the facility are nearing completion and
and metal stud walls are in progress. Building utility slab pours began at the end of June. The first
systems are being installed as we work towards shipments of the Pre-Engineered Building also
a helicopter lift at the end of July and permanent arrived at the end of June and erection of the
power in mid-August. We’ll turn over the first area warehouse began in early July.
to the tenant and their MHE vendors at the end
of September.
On the MKDA jobsite, we are currently preparing
for finish trades to begin their work in the office
area and mechanical piping throughout the
production areas continue. By the end of the
month paving will be complete and landscaping