Page 22 - Paparan KI Sadai_Neat
P. 22
Sadai Integrated Industrial and Port, South Bangka - Indonesia
RATION Smart Sea-Port | Logistics center | Industrial Estate
BANGKA
ABADI
Housing Needs
Projected land requirements needed to be able to facilitate the number of workers as
many as 41,651 people, it is assumed that every 1.5 workers need 1 house unit, thus
27,676 housing units is needed, and if each house is assumed to require 72 m land
2
area is needed approximately 1,999,251 m or approximately: 200 Ha.
2
Given the vast land requirements for housing and the ability of industrial estate
management business entities to experience limitations in the provision of land,
cooperation with housing developers is needed in the construction of residential areas
outside industrial estates, and must meet the requirements or regulatory provisions of
the legislation that applies to the local government.