Sadai Integrated Industrial and Port, South Bangka - Indonesia
                        RATION                                                Smart Sea-Port   |   Logistics center   |   Industrial Estate
                        BANGKA
                        ABADI
                                                        Housing Needs





        Projected land requirements needed to be able to facilitate the number of workers as

        many as 41,651 people, it is assumed that every 1.5 workers need 1 house unit, thus

        27,676 housing units is needed, and if each house is assumed to require 72 m land
                                                                                                                               2
        area is needed approximately 1,999,251 m  or approximately: 200 Ha.
                                                                        2






        Given the vast land requirements for housing and the ability of industrial estate

        management  business  entities  to  experience  limitations  in  the  provision  of  land,

        cooperation with housing developers is needed in the construction of residential areas

        outside industrial estates, and must meet the requirements or regulatory provisions of

        the legislation that applies to the local government.