At  Wallsend,  just  like  many  other  courses,  the  club  is  stagnating  with  declining
                  membership.  It  presents  the  perfect  opportunity  and  location  for  a  substantial
                  investment  to  improve  the  drainage  to  allow  year-round  play  and  to  reconfigure  the
                  course to offer 6, 12 and 18 hole options.

                  The cost to reconfigure the course is some £1.5m, HNL will fund the reconfiguration.
                  STR will manage the redesign works on the Course.

                  STR  will  manage  the  club  and  course  alongside  its  management of  the  Centre.  The
                  parties will share the profits from the course 50/50.

                  STR will grant to HNL, on financial close of the funding required to build the Centre, an
                  option to take a sub-lease of the course of equal duration to and on the same terms as
                  the Centre sublease at a premium of £500,000.

                  CENTRE DELIVERY


                  HNL has appointed a full professional team for the Centre, with RIBA stage 4 design
                  development completed, in addition to the planning application. The current cost plan
                  including fit-out, digital ball tracking equipment & software, ball dispensing equipment
                  and the FF&E,  together with the land and remodeling of the golf course is set at some
                  £16m  including  two  conservative  provisional  sums  to  be  finalised  and  a  value
                  engineering review yet to be completed.

                  After  a  five  contractor  tender  selection  program,  the  preferred  candidate,  Robertson
                  Construction  was  appointed  in  February  2020.  This  early  appointment  will  allow  for
                  maximum contribution by the contractor to provide value engineering, under a design
                  and  build  contract.  Start  on  site  is  planned  for  early  autumn  2021,  with  practical
                  completion planned by late summer 2022.

                  Once completed, the Centre will be managed by STR Management Services Ltd under a
                  management agreement for which heads of terms have been agreed. STR have been
                  fully involved in the design of the first Centre, will sign off on all Centre specifications,
                  attend all testing and handover formalities and prepare a detailed and fully costed pre-
                  opening  plan  for  the  Centre  as  part  of  its  cost plan.  STR’s  Managing  Director,  Chris
                  Sanderson and Chief Accountant Grant O’Neill have had a key role in the preparation of
                  the 5 year P&L, cashflow and balance sheet modeling for HNL.

                  In summer 2018 the HG&L directors Phil Harrison, Ian Robertson and Chris Sanderson
                  visited the first BigShots Centre built in Lubbock Texas.

                  In the UK TopGolf has been operating for 10 years with three  centres in the Greater
                  London area (www.topgolf.com). It now has plans to build a centre in Glasgow and is
                  seeking other sites for new centres which has included its agent approaching STR to
                  purchase the Centurion Park site.