Page 9 - GLNG Week 33 2022
P. 9

GLNG                                             AMERICAS                                             GLNG


       New Fortress Energy expects to bring two




       Brazilian LNG terminals on stream in 2023




        TERMINALS         REPRESENTATIVES of US-based New Fortress  Babitonga Bay, at a site 300 metres offshore from
                          Energy (NFE) reported during a recent confer-  the city of São Francisco do Sul.
                          ence call on its performance in the second quar-  Meanwhile, NFE executives also reported sig-
                          ter of 2022 that it was nearly finished with the  nificant progress on the Barcarena LNG terminal
                          establishment of two new LNG import terminals  project. They said the facility was nearly com-
                          in Brazil.                           plete and would be ready to launch operations in
                            In the call, NFE executives said that work on  2023. This will allow the company to uphold its
                          the offshore Santa Catarina LNG terminal was  commitment to begin supplying regasified LNG
                          very nearly complete. Specifically, they stated  to Alunorte, an aluminium refinery owned by
                          that the facility was about 90% ready and was due  Norsk Hydro (Norway), under a 15-year con-
                          to be finished in the fourth quarter of 2022 and  tract signed in December 2021, they noted.
                          then launched in the first quarter of 2023.  The executives went on to say that NFE had
                            The executives did not comment extensively  started construction work on the 605-MW Bar-
                          on the Santa Catarina LNG project, which is also  carena TPP, which will also use gas imported via
                          known as Terminal Gás Sul (TGS). This terminal  the Barcarena terminal, in the second quarter of
                          will be linked to shore via a 33-km subsea pipe-  2022. Wes Edens, the founder and CEO of the
                          line, which will then be connected to the Gasbol  company, noted that the power station was slated
                          pipeline, the Brazilian section of a larger system  to deliver electricity to local customers under a
                          that pumps imported Bolivian gas into Brazil’s  25-year power purchase agreement (PPA) linked
                          national pipeline network. These links will allow  to JKM, a Brazilian metallurgical concern, and
                          TGS to handle shipments of feedstock bound for  described the PPAs as “super attractive” for NFE.
                          gas-fired thermal power plant (TPPs) in Santa   Edens also suggested that his company might
                          Catarina, Paraná and Rio Grande do Sul states.  be able to deliver gas from its upstream projects
                            The terminal will be based on a floating stor-  in the Gulf of Mexico to the Brazilian terminals
                          age and regasification unit (FSRU) that is capable  in the future. Deliveries could start around mid-
                          of handling the equivalent of 15mn cubic metres  2025, he said, without elaborating.™
                          per day of gas. The vessel has been installed in













































       Week 33  19•August•2022                  www. NEWSBASE .com                                              P9
   4   5   6   7   8   9   10   11   12   13   14