WORK AT HEIGHT WALK ON CEILING

         ● Service penetration through ceiling panels or grids need to be marked on site and
              communicated through Jacobs supervision;

         ● Modification of ceiling components will only be made by Linder

              personnel;

         ● Unauthorized cutting of any ceiling component will result in  disciplinary

              procedures and possible removal from site;

         ● Maintain good housekeeping at all times, cleaning equipment should
              include HEPA vacuum cleaners;


         ● Flammable materials must not to be stored on the ceiling;

         ● All work equipment and work clothing must be clean and suitable for a

              clean room environment;

         ● Short term DAILY storage of materials on the ceiling must not exceed

                           2
                                              2
                                                                2
              150 kg/m  or 330lbs/m  or 1.5 kn.m ;
         ● All packaging must be removed ahead of material being raised on to the
              ceiling and placed on protective material.