               volume of work as quoted by Claimant was Baht 1,354,700.29. However, at the time of the termination
               of the Contract, this work was only 50% completed. Accordingly, the price for the work would then be

               Baht 677,350.15. In addition to the additional work done by Claimant, Claimant also had to do anti-rust
               painting of the roof steel of all the 20 villa houses. Claimant quoted for this work as Additional Work at
               Baht 302,253.60. However, this work was only 90% completed at the time of the termination of the

               Contract. Therefore, the value of the work should be Baht 272,028.24. Accordingly, the Arbitral Tribunal
               is of the opinion that Claimant had done all additional works as alleged in its Notice of Arbitration and

               Statement of Claim, except the Additional Work No. 12. For the fourth issued, regarding this issue, it was
               accepted by the parties that Respondent has paid Claimant two installments of the Advance Payment

               out of the three installments provided in Article 4 . 1  of the Contract, and one interim payment. It was
               clear from the Claimant’s Exhibit 0 6 0 2 0 , sheet 2 4 , that the two installments of the Advance Payment

               paid by Respondent was a total of Baht 40,900,000 (20,450,000 + 20,450,000) and the interim payment
               made by Respondent to Claimant was Baht 1 1 , 7 7 7 , 9 0 5 . 0 9 .   Therefore, the total amount of money

               already paid by Respondent to Claimant was Baht 52,677,905.09 (not Baht 52,877,905.09) minus certain
               deduction of retention. For the last issued, the grand total of the overdue monthly interim payments

               together  with  the  accrued  interest  that  Claimant  is  entitled  to  claim  from  Respondent  is  Baht
               41,721,115.01. The total interest for the late payment of the second and the third installments of the
               Advance Payment is Baht 958,068.49. Accordingly, the grand total of compensation for additional works

               that Claimant is entitled to claim from Respondent is Baht 2 9 , 5 3 2 , 5 8 4 . 8 2 .   Because this amount of
               compensation is fixed by this Arbitral Tribunal on the day of the making of this award, the Arbitral

               Tribunal deems appropriate that this amount shall bear an interest at the rate of 7.5% per annum from
               the date of this award until it will be completely and actually paid by Respondent to Claimant.


               Award

                              Respondent shall pay the following damages to Claimant:
                              1.1    The overdue monthly interim payments together with the accrued interest for
               the amount of Baht 41,721,115.01.

                              However, under Article 4 . 1  of the Contract, Respondent is entitled to deduct the
               Advance Payment made to Claimant from the Interim Payment. The total amount of the two installment

               of Advance Payment paid by Respondent to Claimant was Baht 4 0 , 9 0 0 , 0 0 0 .   Therefore, the overdue
               monthly interim payments together with the accrued interest for the amount of Baht 4 1 , 7 2 1 , 1 1 5 . 0 1