                 included the drill locations, proximity   hole reading results can be viewed in
                 of the drilling to the gasket, as well   the graph.
                 as the volume and speed of sealant
                 injection. The effectiveness of   The results of the mechanical joint
                 different sealants was assessed at   sealing project included:
                 various pressure ranges to allow ULC      The remediation of a 244m section of
                 to develop, refine and train CISBOT   pipeline, with 43 joints remediated
                 operatives on the new remediation   within two weeks. This proactively    FIELD SAMPLE OF 24IN MECHANICAL JOINT MAIN FOR TESTING
                 process before taking the technology   remediated the main at the time
                 into the field.                   of the project to prevent future
                   To seal mechanical joints, the   disruption to customers.
                 systems required minor design        All the identified leaks on the gas
                 modifications including a different   main were eliminated - 0 per cent
                 drill specification, new laser alignment   GIA readings were taken after ULC
                 configurations and a modified sealant   deployed CISBOT to seal the joints.
                 delivery system to support a higher
                 viscosity sealant than what is currently
                 used for lead yarn joints. The proven   Case Study 2
                 launch, navigation inside the pipe and   Remediating SGN’s Network
                 retrieval of CISBOT remain the same.             Taking the          ECO-CABIN CONTROL UNIT TO MINIMISE ENVIRONMENTAL IMPACT
                                                                  technology into the
                 LIVE FIELD TRIAL TESTING & RESULTS               field for a live trial   operation which was prevented by
                 After successful in-house developments           on SGN’s network,   using CISBOT to upgrade the gas
                 and testing, Cadent and SGN identified   a critical 30in medium pressure main   main.
                 sections of their networks that could   was identified in London. The location      Using CISBOT reduced the CO₂
                 be used to perform live environment   was chosen to minimise customer   emissions generated on-site as the
                 remediation and upgrade testing of   disruption as the gas main ran into a   number of excavations were reduced,
                 the new mechanical joint sealing   critical feeder, as well as running near a   which resulted in minimal excess
                 developments. DNV monitored the   primary school. Throughout the project,   material being sent to landfill.
                 process throughout the projects,   ULC hosted SGN’s senior leadership
                 carrying out daily leakage monitoring   team on-site to explain the new   CONTINUOUS IMPROVEMENT
                 during the trials and weekly monitoring   developments and modifications made   At ULC Technologies, we are
                 after the projects were concluded.   to the sealing process. SGN and ULC   continually investing in the
                                                  closely monitored the sealing to ensure   development and deployment of
                                                  the successful remediation of the asset.   revolutionary innovations to meet
                 Case Study 1                                                      the needs of the industry. To date,
                 Remediating Cadent’s Network     The project resulted in:         ULC has successfully sealed over
                                 Cadent identified      One excavation to remediate 30   1km of mechanical joints in the UK
                                 a challenging 18in   mechanical joints, significantly   since the introduction of CISBOT’s
                                 cast iron medium   extending the life of the asset.   extended capabilities, helping improve
                                 pressure gas main   Replacing the gas main would have   operational safety and minimise
                 in Northampton that would be an ideal   been a costly and time-consuming   customer disruption.
                 location for CISBOT mechanical joint        60
                 sealing. This gas main had problematic
                 leaks, which posed significant              50
                 challenges to repair conventionally
                 due to access constraints for the
                 operatives and the requirement for a        40
                 3m-deep excavation. In addition, there
                 were watercourses from the river that       30
                 would have made the traditional repair   Bar Hole Reading in % Gas
                 process complex, costly, and high risk.     20
                 Cadent and ULC identified and mapped
                 out leaking mechanical joints on the        10
                 main before joint sealing commenced,
                 taking gas in the air (GIA) readings.
                 Throughout the two-week sealing   Bar Hole #  0  1   2   3   4   5   6   7   8   9   10   11   12   13   14   15   16   17   18   19
                 project, the new CISBOT process was   Initial Reading       0   0   0   0   0.6   1.5   1   43   0.6   5   0.5   12   0.3   0.5   15   0.2   28   0.3   0
                 monitored and further readings were   Post CISBOT Reading       0   0   0   0   0   0   0   0   0   0   0   0   0   0   0   0   0   0   0
                 taken during and after sealing. The bar
                                                                                   TOWCESTER ROAD, NORTHAMPTON – BAR HOLE READING EAST DIRECTION
                                        FOR MORE INFORMATION, PLEASE VISIT WWW.ULCTECHNOLOGIES.COM
                                        OR CONTACT OUR UK TEAM AT +44 (0)20 3617 4586