Page 16 - WMP_Neat
P. 16
2.4 WMP ENFORCEMENT
Legally, a project is only allowed to commence after approval of the EMP by the DOE (including
approved WMP by PERHILITAN). Based on Figures 2.1 and 2.3, the Terms of Agreement signed
(Agreed) by the proponent to implement WMP will allow PERHILITAN to monitor the mitigation
activities conducted by the proponents for compliance. PERHILITAN’s procedures for compliance
monitoring are summarised in Figure 2.4. Detailed compliance monitoring procedures are
available in the Guidance Document on Compliance Monitoring of WMP for EIA.
At Project Site
WMP Checklist Review
(PERHILITAN)
Review of Compliance
Non-compliance (PERHILITAN)
Notice of Non-compliance
(PERHILITAN)
Improvement
(Project Proponent/Consultant)
Yes
Notice of Compliance
(PERHILITAN)
Compliance
No Enforcement - IP
(PERHILITAN)
Report to DOE
(PERHILITAN)
Back to DOE
Figure 2.4: Steps and procedures adopted by PERHILITAN for compliance monitoring of
WMP mitigation measures based on the Terms of Agreement.
12 GUIDANCE DOCUMENT FOR PREPARATION AND SUBMISSION OF WILDLIFE
MANAGEMENT PLAN (WMP) IN ENVIRONMENTAL IMPACT ASSESSMENT (EIA)