2.2 WILDLIFE IMPACT STUDY IN EIA


            A Wildlife Impact Study (WIS) is part of the EIA study except that PERHILITAN manages the entire
            process of a Wildlife Impact Study. As indicated in Figure 2.1, TOR for an EIA project falls under
            Schedule 2. It needs to be approved by the DOE, where part of TOR (Wildlife Study) needs to be
            reviewed and vetted by an expert representative from PERHILITAN. After the DOE approves TOR,
            the process of the Wildlife Study will be managed by PERHILITAN, following the steps and
            procedures shown in Figure 2.2. The steps begin by applying for the Research Permit before the
            Wildlife Impact Study can commence, followed by submitting the WIS report to PERHILITAN for
            approval. Wildlife Impact Study Report will be reviewed by the Review Officer at PERHILITAN.


                                                                 TOR Approved by DOE


                     Not Approved
                                                                Application of Research Permit
                                                                (Project Proponent/EIA Consultant)
                                                  Approved
                                                                Start Wildlife Impact Study
                                                                (EIA Consultant)


                                                                Submission of EIA Report
                                                                (Project Proponent/EIA Consultant)
                    Amendment
                    of Report
                                                                Report Review by Review Officer
                                                                (PERHILITAN)
                          Not Approved            Approved
                                                                Wildlife Study Report approval letter
                                                                and notice for requirement of WMP
                                                                (PERHILITAN)


                                                                 Back to EIA Procedure




                         Figure 2.2: Steps and procedures adopted by PERHILITAN in managing
                     Wildlife Study process from TOR Approval until Wildlife Study Report approval.


            If PERHILITAN approves the Wildlife Study Report, written approval notification shall be made
            immediately to DOE to complement the whole EIA process for approval. Similarly, if PERHILITAN
            does not approve the Wildlife Study Report, the proponent will be notified in writing and shall be
            given an opportunity to amend the report according to suggestions made by Review Offices. If no
            amendments are made during the prescribed timeframe, the report shall be considered to have
            failed to meet the approval requirements of PERHILITAN. To follow the common practice adopted
            by the DOE, an EIA that falls under Schedule 1 will be managed at the State Level, while an EIA that
            falls under Schedule 2 will be managed at the Federal Level.

            The detailed requirements on how the Wildlife Impact Study must be conducted and the report
            must be prepared for submission to PERHILITAN are available in Guidance Document on Wildlife
            Impact Study for EIA.