Page 22 - booklet draft
P. 22
Yard Development :
D. Sanctioned traffic Facility work of conversion of Siding-1 as UP loop line
(Coaching fit) and Siding 2 as goods loop with R&D facilities was
commissioned on 06.02.2022.
E. Expansion of KTPS (Stage-VII) commissioned on 29.03.22.
F. CT-Orient Phase-II work commissioned on 14.08.22
New Lines :
G. Commissioning of BDCR –Sattupalli (54 Kms) new line-28.05.22
H. Commissioning of 3 line between OPL-JMKT – BGSF (18 kms) 20.07.2022.
rd
I. Commissioning of Sultanabad connectivity to GCT Rani & Others-
26.06.2022.
J. Commissioning of GCT SUH- Shree cements connectivity to siding with VDU
06.09.2022.
Freight
Improving section capacity
1. Tripling of KZJ-BPQ Section:(234 Kms)
Completed in 2022-23(upto Oct): 100 Kms
Target for 2022-23: 93.60 Kms
Balance to be completed in 2022-23 : 73.64 Kms
2. Sectional speed improvement:
Completed:
MTMI-JNPD (Km 0/2 - 77/5) from 50 to 75 kmph.
KRMR-LPJL (km 35/0 – 83/13) from 75 to 90 kmph.
MAGH-WIRR U/D line (Km 142/0 – 159/18) from 100- 110 kmph.
Proposed:
MMZ-PPZ (3rd line – UP line) from 100 to 110 KMPH under HQ’s for
approval
RGPM-KOLR-PTPK (3rd line – UP/DN line) from 100 to 110 KMPH under
HQ’s for approva
3. Loop line speed improvement:
Completed:
Enhancement speed on Loop Line from 15Kmph to 30Kmph at all
stations except JPTN -JNPD section
Pending:
HHZ – Road1- 15 Kmph to be relaxed(Fan Shape Layout)
LPI- Rd 6 – 10 Kmph to be relaxed (Multiple crossovers & Sharp Curve
more than 8 degrees)