Page 25 - booklet draft
P. 25
And also 586 special trains were run for 1738 trips up to the October –
22.
Speed of LBH coaches is enhanced to 130kmph, 22 outgoing trains and
16 incoming trains are run with 130kmph regularly.
A total 18.36kms 03rd line completed up to October – 22 between
BGSF-OPL stations
4. Operational Infrastructure improvement underway
Operational Infrastructure sanctioned:
a) PDPL bypass at KZJ end:
Sanctioned 3 rd line works between KZJ-BPQ under material
modification.(Construction)
Status: Drawings and alignment is approved. Estimates prepared.
Needs to be included for material modification and fund allocation.
b) Remodeling of Jaggayyapeta Town (JPTN) for enhancing of
CSRs and provision of “Y” connectivity towards MRCJ
siding:
Work is sanctioned for three works at JPTN yard under GM-OOT:
A. Restoration of Y-Connectivity Rs.2.484 Cr
B. Provision of full length loading line Rs.2.49 Cr
C. Up-gradation of signaling arrangements of Y –connectivity
Rs.2.49 Cr.
Status: Tenders awarded. LOA issued. TDC- March 2023.
c) Provision of block station:
With standard layout at existing halt station of Gandhipuram between
Karepalli-Chimalpahad in DKJ-MUGR section.
Status: work sanctioned in March2022. Detailed estimates sanctioned.
LOA station building given on 07.07.2022. LOA for bridge work (10 KK)
given on 26.07.22, Track work LOA on 15.07.2022. Cess work LOA-
07.07.22
d) Freight examination facility at Dornakal Jn.
Status: ESP of DKJ is approved for provision of freight examination line,
extension of existing shunting neck to accommodate full length freight
train and provision of sick line shed which are sanctioned in PWP under
PH-4200. As part of 3 rd line works between KZJ-BZA, additional freight
examination line of 800 meters, stabling line of 750 meters, provision of
shunting neck towards KZJ end and augmentation of sick line shed. In
addition to the above, extension of existing dead end spurs of R-10&11
to full length is required for better utilization of these spurs.