LPI Rd5 & Rd 4 - 15 Kmph to be relaxed (multiple Crossovers)
                          HSJ- SC-SNF(Cord line)  15KMPH to be relaxed
                           HSJ- HYB-SC (Cord line)  15KMPH to be relaxed
                          HSJ- Loop line  15KMPH to be relaxed


                     4. PSR removals:

                        Completed:

                          NMPL  yard  30  kmph  to  90  Kmph  after  removal  of  spiked  points  and
                          passing through Main line.
                          PUDR  yard  – (km  61/15-62/21)  from  30  to  90  kmph  for  Empty
                          goods/Coaching and 60 Kmph for loaded goods
                          Permanent Speed Restriction reduction using provision of routing home
                          has been achieved in terminating stations. 15Kmph Speed boards have
                          been removed at BDCR, VKB, and PRLI.


                        Proposed:

                          Proposed  for  removal  of  PSR  between  MKDI-WIRR  (UP- 161/3-160/23)
                          from 75 Kmph to 110 Kmph
                          Proposed for removal of PSR between LPI-HFZ (DN- 166/32- 167/24) from
                          80 Kmph to 90 Kmph
                          Proposed  for  removal  of  PSR  WIRR  Yard  (DN- 160/12-160/16)  from  75
                          Kmph to 110 Kmph


                       Reduction of PDD to less than 60 minutes
                          Target has been set by the division as

                              a. Train Ordering to Train arrival –“0” Mins
                              b. Train Ordering to Train departure – “30” Mins


               Commissioning of RE:


                          RE commissioning between KHNP-PRLI to be done.
                          RE commissioning at VCSG Siding of SEM to be done.
                          RE commissioning at JVRB Siding of PSHP to be done



                       Scaling up of Crack Trains:


                          Crack paths have been identified and  crack  trains  are  being  run  in
                          crack paths
                          Number of Cracks run up to OCT:
                             Year           No of Cracks run Average/day
                             2021-22               4134                19.3
                             2022-23               5127                23.9


                          Crack Crew LR status
                                  Depot        Total Crew Available        Crew LR given
                                   SNF                   272               CT-KZJ – 120
   18   19   20   21   22   23   24   25   26   27   28