BDCR 21.09.22. Tenders to call.
ESP and DPR approved, Consultant submitted BTPS-CSP
3 BTPS-MUGR
connectivity ESP at CE.P&D for approval.
FSR, IPA and ESP are approved. Environmental clearence
Dalmia
4 Cements- received from State government. Mining lease lapsed.
Petition filed in High court/Karnataka. 90% of land
MQR-SEM
acquisition completed.
ESP approved on 17.06.2022, Revised DPR to be
5 Tata Steels –NPL
submitted by the consultant.
RITES to upload Sheet 2&3 in E-Das for approval.
GM/Civil/SCCL on 22.6.22 meeting requested to keep the
6 KK SCCL – BPA
proposal live for 02 years as coal blocks are not alloted to
SCCL.
Varalakshmi – IPA issued on 09.07.21. Observations on revised plan sent
7
OPL to consultant on 18.02.22. Financial disputes.
IPA issued on 09.04.22. Consultant has to submit ESP &
8 Medha – NPL
DPR.
IPA issued on 04.08.21. Consultant has to submit ESP &
9 NCL – SSLM
DPR. Forest clearance yet obtain.