BDCR              21.09.22. Tenders to call.

                                          ESP and DPR approved, Consultant submitted BTPS-CSP
                   3    BTPS-MUGR
                                          connectivity ESP at CE.P&D for approval.
                                          FSR, IPA and ESP are approved. Environmental clearence
                        Dalmia
                   4    Cements-          received from State government. Mining lease lapsed.
                                          Petition filed in High court/Karnataka. 90% of land
                        MQR-SEM
                                          acquisition completed.
                                          ESP approved on 17.06.2022, Revised DPR to be
                   5    Tata Steels –NPL
                                          submitted by the consultant.
                                          RITES to upload  Sheet 2&3  in E-Das for approval.
                                          GM/Civil/SCCL on 22.6.22 meeting requested to keep the
                   6    KK SCCL – BPA
                                          proposal live for 02 years as coal blocks are not alloted to
                                          SCCL.
                        Varalakshmi –     IPA issued on 09.07.21. Observations on revised plan sent
                   7
                        OPL               to consultant on 18.02.22. Financial disputes.
                                          IPA issued on 09.04.22. Consultant has to submit ESP &
                   8    Medha – NPL
                                          DPR.
                                          IPA issued on 04.08.21. Consultant has to submit ESP &
                   9    NCL – SSLM
                                          DPR. Forest clearance yet obtain.