Page 26 - booklet draft
P. 26
Operational Infrastructure Proposed for Sanction:
a) Jaggayyapeta Town (JPTN)-Electronic Interlocking:
It is proposed to execute the work of panel interlocking by utilising the
balance funds allocated to construction organization.
b) In DKJ-BDCR doubling works:
JVRB-Sathupalli line to be connected to BTPD, Rail over Rail at Dornakal by
construction department.
Status: divisional observation made on conceptual plans of proposed
doubling and submitted to Dy.CE.C-III/SC.
c) TXR facility At CT:
Development of TXR facility at CT to avoid empty running to and from SNF
to MQR area
Status: Tenders finalized, LOA issued and ESP under preparations
d) Locally operated Motor points:
Replacement of Manually operated points with locally operated motor
points at SNF yard to ensure safety and to avoid time loss for clamping
and padlocking.
Electrification of Vasavadatta Cement siding (VCSG)/ Seram:
Electrification works on the lead line and in plant was completed in 2013.
Charging could not be done due to objection from local public. This
causing delay in operations and forced to operate diesel traction in
underwire territory.
Provision of individual OHE isolators:
Provision of Individual OHE isolators for each line at 111 stations to facilitate
traffic movement over other lines.
Proposal for extension of trains:
Proposal for extension of trains to ease congestion at TDU and CT stations
with existing lie-over period
Train No. 17664/17663 (NED-TDU-PBN) Express to RC/MALM
Train No. 07659/07660 (SC-CT-SC) MEMU to KLBG
III. GATI SHAKTI TERMINALS 2022-23 Target – 05 GCTs