Page 159 - ADMINISTRATIVE MANUAL
P. 159

159


               The BAC shall determine if each prospective bidder is eligible to participate in the bidding by
               examining  the  completeness  of  each  prospective  bidder’s  eligibility  requirements,  using  a
               non  discretionary  “pass/fail”  criteria,  and  shall  be  determined  as  either  “eligible”  or
               “ineligible”.

               The  BAC  shall  inform  an  eligible  prospective  bidder  that  it  has  been  found  eligible  to
               participate  in  the  bidding.  The  BAC  shall  inform  an  eligible  prospective  bidder  that  it  has
               been found ineligible to participate in the bidding, and the grounds for its ineligibility. Those
               found ineligible have seven (7) calendar days upon written notice or, if present at the time of
               opening of eligibility requirements, upon verbal notification, within which to file a request for a
               reconsideration with the BAC.

               Notwithstanding  the  eligibility  of  a  prospective  bidder,  the  procuring  entity  concerned
               reserves the right to review it qualifications at any stage of the procurement process if it has
               reasonable  grounds  to  believe  that  a  misrepresentation  has  been  made  by  the  said
               prospective  bidder,  or  that  there  has  been  a  change  in  the  prospective  bidder’s  situation
               from the time it submitted its eligibility requirements.

                   b)  Eligibility Check for Infrastructure Projects

                   The determination of eligibility shall be based on the submission of the following:

                   1)  Class “A” Documents
                       a)  Department  of  Trade  and  Industry  (DTI)  business  name  registration  or  SEC
                          registration certificate, whichever may be appropriate under existing laws of the
                          Philippines;
                       b)  Valid and current Mayor’s permit/municipal license.
                       c)  Taxpayer’s Identification Number;
                       d)  Prospective Bidder’s computation for the NECC;
                       e)  Statement of the prospective bidder that is  not “blacklisted” or barred from the
                          bidding  by  the  Government  or  any  of  its  agencies,  offices,  corporations  or
                          LGUSs, including, non-conclusion in the “blacklist:” of the contractors issued by
                          the Construction Industry Authority of the Philippines;
                       f)  Other appropriate license as may be required by the procuring entity concerned;
                       g)  Statement of the prospective bidder of all its ongoing and completed government
                          and private contracts, including contracts awarded but not yet started, if any. The
                          statement shall state for each contract whether said contract is:

                          g.1  Ongoing,  Completed  or  Awarded  but  not  yet  started:  within  the  relevant
                               period, where applicable. The statement shall include, for each contract, the
                               following:

                                  i.   Name of the contract;
                                 ii.   Date of award of the contract;
                                 iii.   Contract duration;
                                iv.   Owner’s name and address;
                                 v.   Nature of work
                                vi.   Contractor’s role (whether sole contractor, sub-contractor, or partner
                                      in a joint venture);
                                vii.   Total contract value at ward;
                               viii.   Date of completion or estimated completion time;
                                ix.   Total contract value at completion, if applicable;
                                 x.   Percentages of planned and actual accomplishments, if applicable;
                                xi.   Value of outstanding works, if applicable