Page 321 - Tech handbook 2019 rev 6 whyperlinks
P. 321

Gaseous Fueled Power Generation Systems
                                          Co-Generation ● Landfill ● Biogas


















































                   c.  Quote Approval
                           i.  INNIO will provide a list of MSA quotes (SEQ).



                                  RE_ MSA
                          ii.    Quotes.msg
                          iii.  SCM will take each quote and look up the forecasted service date on the “MRP Fulfillment” file.
                              If the service is taking place within the correct lead time, SCM will then start the process of
                              approving the quote
                          iv.  SCM will open the parts tracker and create the bill of materials tab for that specific interval using
                              the latest annex.  SCM will then compare the parts required against the quote INNIO provides.
                                 1.  If the part #s and qtys on the quote are correct, SCM will inform INNIO that quote is
                                     approved.
                                         a.  Once INNIO receives approval, the quote will be converted into a SEC by INNIO.
                                         b.  SCM will note the SEQ and SEC numbers on the parts tracker and the “MRP
                                            Fulfillment” file.
                                 2.  If there are discrepancies:
                                         a.   SCM will log them on the “GEJ MSA Discrepancies
                   d.  MSA Fulfilment
                           i.  The MSA’s are managed using a file called, “MRP Fulfillment File”:
   316   317   318   319   320   321   322   323   324   325   326